Railways

Niš – Dimitrovgrad Railway Modernisation

Modernisation and partial realignment of Serbian mainline 106 from Niš to the Bulgarian border at Dimitrovgrad, the Serbian leg of the Corridor X branch toward Sofia. Under construction with European Investment Bank and EU support. Works started in November 2023 on Staničenje – Pirot. No opening date has been announced; Pirot Plus Online (22 July 2026) reports an end-2027 deadline, Sukovo – Dimitrovgrad (10.2 km) largely built and Dolac – Prosek, through the Sićevo gorge, due to start on 1 September 2026. Sources disagree on the total, with EUR 502 million given as the project cost against EUR 268–276 million quoted for individual subprojects.

Total length
96 km
Open today
0 km
Under construction
96 km
Sections
1
Cost for the project as a whole
€428M(2025)whole programmeestimatedMGSI's April-June 2025 ministry work report gives a revised estimated value of about EUR 428 million for the project. The figure is project-wide and includes the Niš railway bypass, which is not drawn in this 96 km lot. The EIB project page gives an earlier EUR 502 million total.
Loading map data…

Sections

Sections of Niš – Dimitrovgrad Railway Modernisation: status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Niš – Dimitrovgrad

Pirot Plus Online (22 July 2026) reports a completion deadline of the end of 2027 for the project's four components. This is a press report of a works deadline, not an official opening date. Trace Group Hold leads the consortium building Sićevo – Dimitrovgrad (with Consorzio Armatori Ferroviari and Start Engineering). Ekstra Auto Transport and China Road and Bridge Corporation build the 22 km Niš bypass from Niš-Ranžirna to Sićevo. The MGSI work report for April-June 2025 gives a new estimated project value of about EUR 428 million; the EIB project page gives EUR 502 million.

Under construction96 km
  1. Nov 11, 2023Construction start
–
  • LoanEuropean Investment Bank, proposed finance of about EUR 341 million.
  • European Union
  • National budget
  • Trace Group HoldBuilder
  • Consorzio Armatori Ferroviari S.C.p.A.Builder
  • Start Engineering JSCBuilder
  • Ekstra Auto TransportBuilder
  • China Road and Bridge CorporationBuilder
–

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • Loan96 km
    1 section
    • European Investment Bank, proposed finance of about EUR 341 million.
  • European Union96 km
    1 section
  • National budget96 km
    1 section

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Corridors

The designations this project is recorded under. Both schemes are kept: the Pan-European corridors are how these projects were described when they were planned, and TEN-T is what EU money is allocated on today.

  • Pan-European Corridor XPan-European

Sources

  1. European Investment Bank: Nis–Dimitrovgrad railway rehabilitation project pipeline
  2. OpenStreetMap: relation 1335433, Магистрална пруга 106
  3. OpenStreetMap contributors: route geometry (ODbL)
  4. Tanjug: Vesić: Počeli radovi na modernizaciji pruge Niš-Dimitrovgrad (11 November 2023)read Sep 25, 2026
  5. Pirot Plus Online: Rekonstrukcija pruge Niš – Dimitrovgrad: Trejs žuri da nadoknadi izgubljeno (22 July 2026)read Sep 25, 2026
  6. Pirot vesti: Stara pruga od Niša Dimitrovgrada polako odlazi u istoriju! Koliko će koštati rekonstrukcija ove deonice, koji su rokovi? (15 November 2023)read Sep 28, 2026
  7. Politika: Vučić prisustvovao početku gradnje železničke obilaznice oko Niša (6 July 2024)read Sep 28, 2026
  8. MGSI: Information on the Ministry's work, April–June 2025 (new estimated value for Niš–Dimitrovgrad project)read Oct 11, 2026