Žilina – Čadca – Czech border railway modernisation (line 106D, corridor VI)

Modernisation of the double-track ŽSR line Žilina – Čadca – Mosty u Jablunkova, part of European rail corridor VI. ŽSR ran it as separate EU-co-financed projects. Žilina – Krásno nad Kysucou was built in 2008–2011 under a Doprastav-led joint venture. Čadca – Svrčinovec – state border was one works contract with TSS GRADE, split into two sections by funding source, and was completed on 12 December 2025. Krásno nad Kysucou – Čadca had only a design project (territorial decision issued on 31 August 2012) and no works contract on the ŽSR project pages. No ŽSR project page covers the Čadca – Skalité branch.

Total length
25 km
Open today
25 km
Sections
3
Cost on record
€72.611M
1 of 3 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of Žilina – Čadca – Czech border railway modernisation (line 106D, corridor VI): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Žilina – Krásno nad Kysucou

Modernisation of the existing double-track line: safety and communication systems, track, overhead line, platforms, bridges, culverts and underpasses. The ŽSR page gives the works contract (no. 56/2008/0) as EUR 153,639,822.1 with the joint venture led by Doprastav, and the project start as 6 June 2008. Its signing-date column shows 30 November 2011, which is the works completion date, so no award date or cost-revision entry is recorded. The page adds that the completion approval proceedings were still under way. The contract was amended by three addenda and five change orders and the accepted price was not exceeded. The supervision contract (Inžinierske združenie Kysuce, EUR 4,383,724) was signed on 2 September 2008. Length measured from OpenStreetMap geometry (Žilina station to Krásno nad Kysucou station); the page states no length.

Opened20 km
  1. Nov 30, 2011Opened
–
  • European UnionCohesion Fund, grant agreement 165/270/2009 of 23 September 2009. Total cost under the grant EUR 158,840,953.10, of which EU EUR 85,877,364.00. Final financial outturn EUR 152,000,120.10.
  • Združenie „Žilina – Krásno“ (Doprastav, a.s.)Builder
Contract value €153.64M
Čadca – Svrčinovec zastávka (section A)

Section A of the Čadca (excluding the station) – Svrčinovec – state border works: about 2.663 km of existing double track, with safety and communication systems, track, overhead line, 2 platforms, rebuilt bridges and culverts and a passenger overpass. The EUR 65,882,867.12 works contract (effective 29 March 2022) covers sections A and B together and is recorded on this lot only. The ŽSR page gives 29 March 2022 as the start of the main activities, which is the contract date, so no construction start is recorded. The ŽSR page does not give the chainage where the works start ("Čadca (mimo)"). The drawn line ends at Svrčinovec zastávka and is cut back along the track to match the stated 2.663 km, so its northern start is approximate. Chainages on sk.wikipedia (Svrčinovec zastávka 281.920, border 284.339) give about 2.42 km for section B and about 4.9 km for sections A and B together.

Opened3 km
  1. Dec 12, 2025Opened
–
  • European UnionConnecting Europe Facility, grant agreement INEA/CEF/TRAN/M2019/2106494 (signed 26 October and 16 November 2020). Total cost under the grant EUR 46,921,455, of which EU EUR 39,883,237 and state budget EUR 7,038,218. Spent by 30 June 2026: EUR 55,491,354.16 from all sources.
  • Združenie „ŽSR, KYSUCE“ – TSS GRADE, a.s.Builder
Contract value €65.883M
Svrčinovec zastávka – Czech border (section B)

Section B of the same works contract as section A (EUR 65,882,867.12, recorded on the Čadca – Svrčinovec lot): modernisation of the double-track line 106D from Svrčinovec zastávka to the Czech border, with three retaining walls at Svrčinovec and the halt rebuilt. ŽSR split it into phase 1 (OPII, main activities 29 March 2022 to 30 November 2023) and phase 2 (Programme Slovensko, from 1 December 2023); the phase 2 page records completion by 12 December 2025. Length measured from OpenStreetMap geometry (Svrčinovec zastávka to the border node); the pages state no length. The two funding entries are the EU shares of phase 1 and phase 2.

Opened2 km
  1. Dec 12, 2025Opened
–
  • European UnionPhase 1: Operational Programme Integrated Infrastructure 2014–2020, grant agreement Z311011BID1 effective 1 January 2022. Total cost under the grant EUR 5,516,262.81, of which EU EUR 4,688,823.39.
  • European UnionPhase 2: Programme Slovensko, grant agreement Z401301FNZ effective 21 May 2024. Total cost under the grant EUR 29,343,243.72, of which EU EUR 24,941,787.16. Spent by 30 June 2026: EUR 29,317,577.21 from all sources.
  • Združenie „ŽSR, KYSUCE“ – TSS GRADE, a.s.Builder
–

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union28 km
    4 sections
    • Cohesion Fund, grant agreement 165/270/2009 of 23 September 2009. Total cost under the grant EUR 158,840,953.10, of which EU EUR 85,877,364.00. Final financial outturn EUR 152,000,120.10.
    • Connecting Europe Facility, grant agreement INEA/CEF/TRAN/M2019/2106494 (signed 26 October and 16 November 2020). Total cost under the grant EUR 46,921,455, of which EU EUR 39,883,237 and state budget EUR 7,038,218. Spent by 30 June 2026: EUR 55,491,354.16 from all sources.
    • Phase 1: Operational Programme Integrated Infrastructure 2014–2020, grant agreement Z311011BID1 effective 1 January 2022. Total cost under the grant EUR 5,516,262.81, of which EU EUR 4,688,823.39.
    • Phase 2: Programme Slovensko, grant agreement Z401301FNZ effective 21 May 2024. Total cost under the grant EUR 29,343,243.72, of which EU EUR 24,941,787.16. Spent by 30 June 2026: EUR 29,317,577.21 from all sources.

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. ŽSR: Modernizácia železničnej trate Žilina – Krásno nad Kysucouread Oct 10, 2026
  2. ŽSR: Modernizácia železničného úseku Čadca – Svrčinovec zastávka (vrátane)read Oct 10, 2026
  3. ŽSR: Modernizácia koridoru, štátna hranica ČR/SR – Čadca – Krásno nad Kysucou (mimo), úsek Svrčinovec – štátna hranica SR/ČR (1. fáza)read Oct 10, 2026
  4. ŽSR: Modernizácia koridoru, štátna hranica ČR/SR – Čadca – Krásno nad Kysucou (mimo), úsek Svrčinovec – štátna hranica SR/ČR (2. fáza)read Oct 10, 2026
  5. ŽSR: Modernizácia koridoru, štátna hranica ČR/SR – Čadca – Krásno nad Kysucou, (vonkajšia) železničná trať (design project)read Oct 10, 2026
  6. OpenStreetMap contributors (ODbL): railway=rail ways, Žilina – Čadca – Svrčinovec – Czech borderread Oct 10, 2026