Impresa Pizzarotti

Romania
Sections
4
Length
118 km
Median slip
+46 mo
Median overrun

Slip measured on 3 of 4 sections built.

No section this firm built records both an estimate and a final cost.

Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.

Joint ventures worked through

  • Impresa Pizzarotti – Retter

Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.

Sections built

SectionCountryStatusLengthOpenedSlip
A0 Bucharest Ring Motorway / North half-ring: DN1 – A1 (via Buftea)RomaniaUnder construction18 km
A10 motorway (Sebeș–Turda) / Lot 1: Sebeș (A1) – Alba Iulia NorthRomaniaOpened17 kmDec 2020+53 mo
A3 Bucharest–Brașov Motorway / Bucharest – PloieștiRomaniaOpened62 kmJul 2012+46 mo
A7 Motorway (Moldavia Motorway) / Dumbrava (A3) – Mizil (Ploiești–Buzău lot 1)RomaniaOpened21 kmDec 2024+15 mo

Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.