Tirrena Scavi

Romania

Name variants are not merged

Unregistered spelling

Sections
6
Length
166 km
Median slip
+46 mo
Median overrun

Slip measured on 3 of 6 sections built.

No section this firm built records both an estimate and a final cost.

Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.

Joint ventures worked through

  • Tirrena Scavi – Condotte
  • Tirrena Scavi – Condotte – Cossi

Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.

Sections built

SectionCountryStatusLengthOpenedSlip
A1 Bucharest–Nădlac Motorway / Lugoj – Deva (lot 1)RomaniaOpened28 kmDec 2015
A1 Bucharest–Nădlac Motorway / Timișoara – LugojRomaniaOpened35 kmDec 2015
A10 motorway (Sebeș–Turda) / Lot 3: Aiud – DeceaRomaniaOpened13 kmJul 2018+32 mo
A3 Bucharest–Brașov Motorway / Bucharest – PloieștiRomaniaOpened62 kmJul 2012+46 mo
A6 Lugoj–Calafat Motorway / Balinț (A1) – LugojRomaniaOpened11 kmDec 2013
Craiova–Pitești Expressway (DEx12) / Craiova – BalșRomaniaOpened18 kmNov 2024+46 mo

Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.