Slovenia

as of Oct 2026

Total open
691 km#10 / 22
Under construction
27 km#15 / 19
Planned
18 km
Projects
10
km per 1,000 km²: 34.1#1 / 22km per million people: 323.8#1 / 22

Measured against 20,273 km² and 2,135,107 inhabitants (Jan 2026).

By category

Highways
561 km#10 / 21
planned 18 km
7 sections
Railways
127 km#10 / 16
building 27 km
3 sections
Tunnels
4 km#3 / 5
1 section

Network growth

Busiest decade: the 2000s, with 372 km opened.

Kilometres opened per decade in Slovenia, by category
kmHighwaysRailwaysTunnels
2000s372 km372 km0 km0 km
2010s298 km189 km109 km0 km
2020s22 km0 km18 km4 km
2000
2010
2020
HighwaysRailwaysTunnels

Mapped sections

Loading map data…

Delivery record

Cost and schedule outcomes for this country's sections, measured exactly as on the performance page.

Median slip
–n=0
On time
–
Median overrun
–n=0
Sections
11

Furthest behind schedule

–

Delivered on time or early

No section here opened on or before its contract date.

Largest cost overruns

No section here records both an estimate and a final cost.

At or under budget

No section here came in at or under its estimate.

Openings timeline

Projects in Slovenia

Sources