D49 motorway (Hulín – Fryšták – Vizovice)
Motorway from the D1/D55 interchange at Hulín east towards Zlín and the Slovak border. ŘSD stavba 4901 Hulín – Fryšták (17.3 km) was started in 2008, stopped in 2010 after complaints and lawsuits and resumed in December 2021. Its first part to Holešov opened on 19 December 2024 and the rest to a temporary connection to road II/490 at Fryšták on 17 June 2026. Sections 4902.1, 4902.2, 4902.3 and 4903.1 (Fryšták – Lípa – Vizovice, 17.7 km in all) are in preparation, with the extent from the ŘSD leaflets drawn along the OpenStreetMap proposed line. The end of the route between Vizovice and the Slovak border was moved in autumn 2023 to the I/49 road class and is not drawn. Lot lengths are the ŘSD figures; the drawn centreline of the two 4901 parts is about 0.9 km shorter in total because it starts at the Hulín junction node, east of the D1.
- Total length
- 35 km
- Open today
- 17 km
- Sections
- 6
Sections
| Sections | Status | Length | Timeline | Cost | Funding | Contractors | Contract terms |
|---|---|---|---|---|---|---|---|
| Hulín – Holešov (4901, part 1) ŘSD stavba 4901, first part, from MÚK Hulín to MÚK Holešov. The 2026 leaflet gives its length as cca 9.8 km; the 12/2024 leaflet says 9.5 km in one place and cca 9.8 km in another. Construction began in September 2008, stopped in July 2010 and resumed in December 2021. The contractor is the Sdružení Hulín–Fryšták joint venture (Skanska DS, Eurovia, Metrostav, DSP, Porr). The contract price of the whole stavba 4901, both parts together, is 5 959 599 028 Kč excluding VAT (contract from 2008); it is not split between the parts, so no lot value is recorded. The drawn centreline starts at the Hulín junction node and is about 1.3 km shorter than the sourced length. | Opened | 10 km |
| – | – |
| – |
| Holešov – Fryšták (4901, part 2) ŘSD stavba 4901, second part, 7.5 km from MÚK Holešov to a temporary connection to II/490 south of Fryšták. Opened on 17 June 2026 for early use under a decision of the Dopravní a energetický stavební úřad; the ceremonial opening was planned for 20 June. The May 2026 leaflet had forecast 06/2026 and recorded the building permit for 11 structures being annulled in July 2025 and reissued on 20 March 2026. The contractor is the Sdružení Hulín–Fryšták joint venture. The contract price of the whole stavba 4901 is 5 959 599 028 Kč excluding VAT (contract from 2008) and is not split between the parts; zdopravy.cz gave about 6.5 billion Kč excluding VAT for this section, which is not recorded as a lot value because the basis is not stated. The 2008 construction start is for the whole stavba. | Opened | 8 km |
| – | – |
| – |
| Fryšták – Lípa, stage 1 (4902.1) ŘSD stavba 4902.1 from km 17.300 behind the Dolní Ves bridge to km 19.000: the permanent MÚK Fryšták and the 3.366 km Zlín feeder (relocated II/490). Category D 25.5/120. The ŘSD stavby dataset (export of 2026-05-05) lists it as in preparation, with construction planned for 2029–2032 (years only). Drawn along the OpenStreetMap proposed line, cut at the leaflet chainage from the end of stavba 4901. | Planned | 2 km | – | – | – | – | – |
| Fryšták – Slušovice, stage 2 (4902.2) ŘSD stavba 4902.2 from km 19.000 behind MÚK Fryšták to km 28.300, where it ends provisionally at a roundabout on II/491 before Slušovice. Category D 25.5/120. After it, through traffic towards Vizovice is to use II/491. The ŘSD stavby dataset lists it as in preparation, with construction planned for 2029–2032 (years only). Drawn along the OpenStreetMap proposed line, cut at the leaflet chainage. | Planned | 9 km | – | – | – | – | – |
| Slušovice – Lípa, stage 3 (4902.3) ŘSD stavba 4902.3 from km 28.300 to km 32.000, with MÚK Lípa 1 and Lípa 2, viaducts over the Dřevnice (734 m) and Lutoninka (815 m and 853 m) and a provisional connection to I/49. Category D 26.0/130. The leaflet says preparation is not continuing for now because the route beyond Lípa is unclear. The ŘSD stavby dataset lists construction planned for 2031–2034 (years only). Drawn along the OpenStreetMap proposed line, cut at the leaflet chainage. | Planned | 4 km | – | – | – | – | – |
| Lípa – Vizovice (4903.1) ŘSD stavba 4903.1 from km 32.000 to km 35.000, with a 630 m gallery at Zádveřice and MÚK Vizovice. Category D 26.0/130. It replaces a stretch of the two-lane I/49. The ŘSD stavby dataset lists construction planned for 2033–2036 (years only). Drawn along the OpenStreetMap proposed line, cut at the leaflet chainage; the line ends at the Vizovice junction. | Planned | 3 km | – | – | – | – | – |
Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.
Related projects
- HighwaysD0 Prague Ring Road (Pražský okruh)Same contractor: Eurovia, Metrostav, Porr, Skanska
- HighwaysD3 motorway (Hričovské Podhradie – Žilina – Čadca – Polish border)Same contractor: Eurovia, Metrostav, Porr, Skanska
- HighwaysD11 motorway (Praha – Hradec Králové – Jaroměř – Trutnov – Polish border)Same contractor: Eurovia, Metrostav, Porr
- HighwaysD35 motorway (Sedlice – Olomouc – Lipník nad Bečvou)Same contractor: Eurovia, Metrostav, Skanska
- HighwaysD48 motorway (Bělotín – Nový Jičín – Frýdek-Místek – Žukov)Same contractor: Eurovia, Metrostav, Porr
- HighwaysD6 motorway (Praha – Karlovy Vary)Same contractor: Eurovia, Metrostav, Porr
Sources
- ŘSD: Informační leták, D49 stavba 4901 Hulín – Fryšták (12/2024, 1. část uvedena do provozu)read Oct 10, 2026
- ŘSD: Informační leták, D49 stavba 4901 Hulín – Fryšták, 2. část (05/2026)read Oct 10, 2026
- ŘSD: Informační leták, D49 4902.1 Fryšták – Lípa, 1. etaparead Oct 10, 2026
- ŘSD: Informační leták, D49 4902.2 Fryšták – Lípa, 2. etaparead Oct 10, 2026
- ŘSD: Informační leták, D49 4902.3 Fryšták – Lípa, 3. etaparead Oct 10, 2026
- ŘSD: Informační leták, D49 4903.1 Lípa – Vizoviceread Oct 10, 2026
- ŘSD: dataset staveb (stavby-linestring, export 2026-05-05), D49 4902.1, 4902.2, 4902.3 and 4903.1 as V přípravěread Oct 10, 2026
- Zdopravy.cz: 18 let čekání dovršeno. ŘSD otevřelo zbývající část „začarovaného“ úseku dálnice D49 Hulín – Fryšták (17. 6. 2026)read Oct 10, 2026
- Wikipedia (cs): Dálnice D49, Výstavba and Přehled úsekůread Oct 10, 2026
- OpenStreetMap contributors: route geometry (ODbL)read Oct 10, 2026