Kalamata – Rizomylos – Pylos – Methoni road axis
Road axis in Messinia from Kalamata by way of Rizomylos and Pylos to Methoni, 48.7 km in three sections, partly new alignment and partly upgrade of existing national roads (EO 82, EO 9). Built as a public-private partnership: contract signed in April 2023 with INTRAKAT – AKTOR Concessions, 30 years (4 of construction, 26 of maintenance and operation), EUR 239.2 million excluding VAT. Works were in full progress on 2 June 2025.
- Total length
- 49 km
- Open today
- 0 km
- Sections
- 3
Sections
| Sections | Status | Length | Timeline | Cost | Funding | Contractors | Contract terms |
|---|---|---|---|---|---|---|---|
| Kalamata – Rizomylos Kalamata city exit to the Rizomylos connection (chainage 16+411), 16.4 km. The concession documents describe it as an improvement of the existing road network, and the first 20 km or so of the axis as upgrading of existing roads (sditforum.gr). The sources describe the axis as having separated carriageways on part of its length and non-separated on the rest, without splitting this by section, and one calls it a fast-traffic road with two lanes per direction. OpenStreetMap carries the works as highway=construction (construction=primary) and the existing EO 82 as highway=primary, lanes=2. The axis includes a 4 km route bypassing Messini (ypodomes.com, 2 June 2025), which the source does not place in a section. Drawn geometry follows existing EO 82 and construction ways, cut at the sourced chainage; the start point is approximate. The contract was signed in April 2023 (ypodomes.com, 22 April 2023; another source gives 24 April), recorded here as the award date. Four years of construction is the whole contract's figure. A ministry decision reported on 7 December 2025 sets the planned operating date at 8 November 2028 and the completion deadline at November 2029; the ministry statement is cited through a secondary source. | Under construction 42 of 48 contracted months | 16 km |
| – |
|
| 48 mo execution |
| Rizomylos – Pylos Rizomylos to Pylos. Ypodomes.com gives 24.4 km, which sums with the other two sections to the stated 48.7 km; other reports give 25.7 km. Per sditforum.gr the first 20 km or so of the axis are upgrades and the remainder new road, so this section mixes both. The cross-section is not stated per section: separated and non-separated carriageways both occur on the axis (ypodomes.com). OpenStreetMap shows Φιλιατρά – Πύλος ways under construction with lanes=2 (construction=primary) and a Καλαμάτας – Πύλου alignment tagged construction=trunk with bridges east of Pylos. In late 2025 the ministers inspected bridges G1 (190 m), G2 (230 m) and G3 (202 m); the last private land parcels for two sections were handed over only in July 2025. Drawn geometry follows existing EO 82 and construction ways and is about 8% longer than the sourced length. The contract was signed in April 2023 (ypodomes.com, 22 April 2023; another source gives 24 April), recorded here as the award date. Four years of construction is the whole contract's figure. A ministry decision reported on 7 December 2025 sets the planned operating date at 8 November 2028 and the completion deadline at November 2029; the ministry statement is cited through a secondary source. | Under construction 42 of 48 contracted months | 24 km |
| – |
|
| 48 mo execution |
| Pylos – Methoni Chainage 0+000 to 7+900, ending at the northern entrance of Methoni. Upgrade of the existing national road Pylos – Methoni (EO 9, sditforum.gr). The cross-section is not stated for this section; OpenStreetMap still shows the road as highway=primary, lanes=2, with no construction tags. The start point is placed 7.9 km before the Methoni end of the drawn line. The contract was signed in April 2023 (ypodomes.com, 22 April 2023; another source gives 24 April), recorded here as the award date. Four years of construction is the whole contract's figure. A ministry decision reported on 7 December 2025 sets the planned operating date at 8 November 2028 and the completion deadline at November 2029; the ministry statement is cited through a secondary source. | Under construction 42 of 48 contracted months | 8 km |
| – |
|
| 48 mo execution |
Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.
Funding
- Public-private partnership49 km3 sections
- Public-private partnership: 30-year contract, 4 years of construction and 26 of maintenance and operation, with INTRAKAT – AKTOR Concessions. No tolls (ypodomes.com, 22 April 2023).
A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.
Related projects
- HighwaysBOAK Northern Crete Motorway (Kissamos – Agios Nikolaos)Same contractor: Aktor, Aktor Concessions, INTRAKAT
- HighwaysA3 Struma MotorwaySame contractor: Aktor
- HighwaysA1 Motorway Athens – Thessaloniki – Evzonoi (PATHE)Same contractor: Aktor
- HighwaysA2 Egnatia Odos (Igoumenitsa – Kipoi)Same contractor: Aktor
- HighwaysA29 Siatista – Kastoria – KrystallopigiSame contractor: Aktor
- HighwaysA8 Olympia Odos MotorwaySame contractor: Aktor
Sources
- Ypodomes.com: Υπογραφή της σύμβασης για τον οδικό άξονα Καλαμάτα – Πύλος – Μεθώνη (22 April 2023)read Oct 5, 2026
- Ypodomes.com: Οδικός άξονας Καλαμάτα – Πύλος – Μεθώνη, σε πλήρη εξέλιξη τα έργα της AKTOR (2 June 2025)read Oct 5, 2026
- Ypodomes.com: Πώς προχωρά η κατασκευή του οδικού άξονα Καλαμάτα – Ριζόμυλος – Πύλος – Μεθώνη (17 November 2025)read Oct 5, 2026
- Anagnostis.org: Τότε θα είναι έτοιμος ο οδικός άξονας Καλαμάτα – Ριζόμυλος – Πύλος – Μεθώνη (7 December 2025)read Oct 5, 2026
- ΣΔΙΤ Forum: Οδικός άξονας Καλαμάτα – Ριζόμυλος – Πύλος – Μεθώνηread Oct 5, 2026
- OpenStreetMap contributors (geometry, ODbL)read Oct 5, 2026
Figures last checked against their sources in Oct 5, 2026.