M6 motorway (Budapest – Dunaújváros – Szekszárd – Bóly – Ivándárda)

Motorway along the right bank of the Danube from the M0 ring at Budapest to the Croatian border at Ivándárda, where it meets the A5. Sections opened from 2006 (Érdi tető – Dunaújváros) to 2025 (Lippó – Ivándárda). Three sections were built under PPP concessions; the M60 branch to Pécs is a separate project. Lots follow the opening dates and concession sections, cut at mapped junctions. Lengths are measured from OpenStreetMap unless a page figure is stated in the lot note.

Total length
194 km
Open today
194 km
Sections
6
Loading map data…

Sections

Sections of M6 motorway (Budapest – Dunaújváros – Szekszárd – Bóly – Ivándárda): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
M0 – Érdi tető

Opened on 23 September 2008, after the section beyond Érdi tető. Length (7 km) from the kilometre markers in the hu.wikipedia junction list (M0 junction at km 15, Érdi tető at km 22); the drawn centreline measures about 6.5 km. No concessionaire or builder is named for this stretch; the article says Magyar Közút Nonprofit Zrt. operates it.

Opened7 km
  1. Sep 23, 2008Opened
––––
Érdi tető – Dunaújváros

Length measured from OpenStreetMap geometry. Opened on 11 June 2006, the first section of the M6. Concession company M6 Duna Autópálya Koncessziós Zrt., founded in 2004 by Bilfinger Berger Project Investments GmbH, Porr Infrastruktur GmbH and Swietelsky International Baugesellschaft GmbH; the page does not name the builders. The en.wikipedia opening list gives 68 km for this section; it is not used because the hu.wikipedia junction list places Érdi tető at km 22 and the M8 junction at km 75, about 53 km apart.

Opened54 km
  1. Jun 11, 2006Opened
––
  • M6 Duna Autópálya Koncessziós Zrt.Concessionaire
–
Dunaújváros – Szekszárd

Length measured from OpenStreetMap geometry. Opened on 31 March 2010, the same day as Szekszárd – Bóly: hu.wikipedia gives that date for Dunaújváros – Bóly and Index (31 March 2010) reports this section opened that day on a last-minute temporary permit. Concession company M6 Tolna Autópálya Koncessziós Zrt.; the page does not name the builders. The cut between this lot and the next is the Szekszárd-dél junction (km 151), an assumption: the page names the concession split at Szekszárd without a junction.

Opened75 km
  1. Mar 31, 2010Opened
––
  • M6 Tolna Autópálya Koncessziós Zrt.Concessionaire
–
Szekszárd – Bóly

Length measured from OpenStreetMap geometry. Opened on 31 March 2010 and ends at the M60 split near Bóly (km 191.6). Concession company Mecsek Autópálya Koncessziós Zrt., formed by Strabag AG, Colas S.A., Bouygues Travaux Publics S.A., John Laing Infrastructure Limited and Intertoll-Europe Zrt.; the page does not name the builders. Four tunnel pairs: Bátaszék 1,331 m, Geresd 399 m, Baranya 865 m and Véménd 418 m (3.01 km per carriageway), and nine larger bridges. From km 191.6 the main carriageways were not built and traffic ran on the collector lanes until the extension towards the border.

Opened39 km
  1. Mar 31, 2010Opened
––
  • Mecsek Autópálya Koncessziós Zrt.Concessionaire
–
Bóly – Lippó

Length measured from OpenStreetMap geometry. Opened on 2 May 2024. NIF Zrt. signed the contract for the whole Bóly – Ivándárda stretch on 12 December 2020 with Strabag Építő Kft. and Duna Aszfalt Út és Mélyépítő Kft. for more than HUF 90 billion; the page does not say whether that is net or gross and it covers both lots, so no figure is recorded. Works area handed over and archaeology from 10 February 2021, earthworks planned from late March 2021; contract deadline May 2024. Ends at the Lippó junction.

Opened15 km
  1. Dec 12, 2020Tender awarded
  2. May 2, 2024Opened
––
  • Strabag Építő Kft.Builder
  • Duna Aszfalt Út és Mélyépítő Kft.Builder
–
Lippó – Ivándárda

Last 5 km to the Croatian border at Ivándárda, handed over on 6 October 2025 with the Croatian A5 section from Pélmonostor to the border; traffic started on 7 October. Length (5 km) as stated in the hu.wikipedia article; the drawn centreline measures about 6.5 km. Same contract and contractors as Bóly – Lippó (see that lot for the contract).

Opened5 km
  1. Dec 12, 2020Tender awarded
  2. Oct 7, 2025Opened
––
  • Strabag Építő Kft.Builder
  • Duna Aszfalt Út és Mélyépítő Kft.Builder
–

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Related projects

Sources

  1. Wikipedia (hu): M6-os autópálya (Magyarország), sections, concessions, tunnels, Bóly–Ivándárda constructionread Oct 10, 2026
  2. 24.hu: Vége az építkezésnek: új autópálya köti össze Magyarországot Horvátországgal (6 October 2025)read Oct 10, 2026
  3. Index: Egy órával közelebb került Pécs Budapesthez (31 March 2010)read Oct 10, 2026
  4. OpenStreetMap: ways ref M6 (network HU:motorway), Overpass query 2026-10-10read Oct 10, 2026
  5. OpenStreetMap contributors: route geometry (ODbL)read Oct 10, 2026