D10 and DC12 expressways: Sveta Helena – Vrbovec – Križevci and Vrbovec – Bjelovar – Virovitica

Two expressways of the Podravina Y planned by Hrvatske ceste. The D10 runs from the A4 at Sveta Helena past Vrbovec to Križevci, 35 km open in 2002, 2007 and 2016, with a 7.5 km two-lane extension to Kloštar Vojakovački under construction. The DC12 branches off at Vrbovec 2 towards Bjelovar and Virovitica: 10.6 km to Farkaševac opened in April 2019, the rest to Bjelovar, Bulinac and Virovitica is under construction or tendered. Kuna amounts are given in the lot notes only.

Total length
97 km
Open today
46 km
Under construction
39 km
Sections
10
Cost on record
€87.932M
2 of 10 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of D10 and DC12 expressways: Sveta Helena – Vrbovec – Križevci and Vrbovec – Bjelovar – Virovitica: status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
D10 Sveta Helena – Vrbovec 1

First section of the D10, from the A4 at the Sveta Helena interchange to Vrbovec 1. The opening year comes from the 2016 report on the Gradec – Križevci opening, which gives no day. The 8.0 km is the chainage of Vrbovec 1 in the English Wikipedia exit list, counted from Sveta Helena.

Opened8 km
  1. 2002Opened
––––
D10 Vrbovec 1 – Gradec

Four-lane bypass of Vrbovec with four grade-separated junctions, opened by Deputy Prime Minister Jadranka Kosor on 3 August 2007. It includes the Vrbovec 2 interchange, where the DC12 branches off. The town of Vrbovec reports 15.15 km and the Ministry 15.5 km. Cost about 330 million kuna (HRK). Strabag Hrvatska was the lead contractor.

Opened15 km
  1. Aug 3, 2007Opened
––
  • Strabag HrvatskaBuilder
–
D10 Gradec – Križevci

Opened on 2 September 2016 with a total investment of 595 million kuna (HRK) and 15 structures: 6 bridges, 3 viaducts, 4 overpasses, 1 underpass and 1 wildlife crossing. The report is dated the day of the opening. The mapped carriageway measures about 10.9 km against the 12.5 km given by the source.

Opened13 km
  1. Sep 2, 2016Opened
––––
D10 Križevci – Kloštar Vojakovački

Two-lane extension of the expressway north from Križevci. Hrvatske ceste told Hina in October 2026 that the contractor asked for an extension to 23 December 2026, which the supervision service agreed, and that the contract value of 30.6 million euro excluding VAT is not expected to be exceeded. The 30-month term announced in October 2022 pointed to 2025. The route towards Koprivnica is in design.

Under construction
48 of 30 contracted months
18 months past the contract date
8 km
  1. Nov 2020Tender awarded
  2. Oct 26, 2022Construction start
  3. Dec 23, 2026Expected opening
––
  • KamgradBuilder
30 mo execution · Contract value €30.6M
DC12 Vrbovec 2 – Farkaševac

First section of the DC12, opened on 16 April 2019 after about ten years of works. Cost 349 million kuna (HRK) excluding VAT for construction and equipment. Freight vehicles over 7.5 tonnes were not allowed at opening. Works on the whole route were officially opened on 27 April 2009, and the Bauštela report dates the first works on this section to 2010. The mapped road starts at the first way mapped as DC12, about 400 m south of the D10 mainline.

Opened11 km
  1. 2010Construction start
  2. Apr 16, 2019Opened
––––
DC12 Farkaševac – Breza

First 5 km of the Farkaševac – Bjelovar section. In November 2025 the press reported them as formally finished but closed to traffic, and Bauštela repeated in September 2026 that Kamgrad built them. The road cannot be used until the 11.8 km to Bjelovar are done; the Minister said in January 2026 that the aim is to finish Farkaševac – Bjelovar by the end of 2026. In March 2022 the mayor of Bjelovar expected this part by the end of 2022. The mapped road measures about 5.6 km to the end of the built OpenStreetMap ways.

Under construction5 km
  1. 2020Construction start
––
  • KamgradBuilder
–
DC12 Breza – Bjelovar

Remaining 11.8 km to the Bjelovar interchange, with a single carriageway. The contract with Kamgrad and Pedom Asfalti was signed in July 2021 and a 30-month term did not change when an addendum for additional works raised it by almost 5 million euro in July 2026. Bjelovar.live reported the contractor introduced to the site on 30 September 2022, while Bauštela dates the works from 2023. The original term would have ended in January 2026; flood and groundwater problems moved it to summer, and Bauštela mentions an unofficial 2027. In January 2026 the Minister said the aim is the end of 2026. The 49.9 million euro quoted for the whole 17 km Farkaševac – Bjelovar section in other press covers both parts and is not recorded as this lot's cost.

Under construction
49 of 30 contracted months
19 months past the contract date
12 km
  1. Jul 2021Tender awarded
  2. Sep 30, 2022Construction start
  3. ≈2025Expected openingProjected from contract
––
  • KamgradBuilder
  • Pedom AsfaltiBuilder
30 mo execution · Contract value €35.13M
DC12 Bjelovar – Bulinac (stages 1A and 1B)

Stages 1A (km 0+000 to 5+000) and 1B (to km 9+360), 9.38 km with a single carriageway, 5 bridges, 2 overpasses and 1 underpass, designed for 100 km/h. Stage 1A continues the Farkaševac – Bjelovar section at its km 27+530. Works began at the future Bjelovar interchange on 27 January 2026 and the term is 30 months. The stages end short of the Bulinac interchange, where the next lot continues. Land and property procedures delayed the start for more than a year after signing. The mapped road measures about 10.4 km because the cut at the end of stage 1B is approximate.

Under construction
9 of 30 contracted months
9 km
  1. 2024Tender awarded
  2. Jan 27, 2026Construction start
  3. ≈2028Expected openingProjected from contract
–
  • European UnionCohesion Fund, Competitiveness and Cohesion Programme 2021–2027: grant agreement signed 27 January 2026 for the whole Bjelovar – Bulinac – Velika Pisanica project (EUR 70 million from the Cohesion Fund, EUR 12.42 million national co-financing, eligible costs EUR 107.45 million; the press gives a project value of EUR 134 million). It covers this lot and the next.
  • Zagorje gradnjaBuilder
  • Texo moliorBuilder
30 mo execution · Contract value €45.01M
DC12 Bulinac – Velika Pisanica (stages 1C and 2A)

Stages 1C and 2A, 11.37 km from km 9+360 across the new Bulinac interchange (with a crossing of the D28) to the Velika Pisanica interchange, with two viaducts, a bridge and several overpasses. The tender gives 4.89 km to the Bulinac interchange and 6.50 km from there, and a 30-month term for the selected contractor. In January 2026 Hrvatske ceste put the estimate at 64 million euro. The mapped line follows the OpenStreetMap construction and proposed ways and measures about 10.6 km.

Tendered11 km–
  • Estimated €61.54Mworks onlyestimatedEstimated value of the tender; the VAT basis and price year are not stated.
  • European UnionCohesion Fund, Competitiveness and Cohesion Programme 2021–2027: grant agreement signed 27 January 2026 for the whole Bjelovar – Bulinac – Velika Pisanica project (EUR 70 million from the Cohesion Fund, EUR 12.42 million national co-financing, eligible costs EUR 107.45 million; the press gives a project value of EUR 134 million). It covers this lot and the previous one.
––
DC12 Špišić Bukovica – Virovitica

Section from the Špišić Bukovica interchange to Virovitica, 5.6 km, the part of the DC12 built from the Virovitica side. The press gives a project value of 28.9 million euro, which is not recorded as a contract value. In November 2025 it was due to finish by the end of the year and was about half a year late; Osijek-Koteks builds the Virovitica interchange under a separate contract. The section between Špišić Bukovica and Bjelovar (about 19 km after Velika Pisanica) is in design and is not drawn. In June 2026 the Virovitica-Podravina county prefect said the works on the section were finished, and in August 2026 the mayor of Virovitica also called it finished; no opening date has been found, so the lot stays under construction. The mapped road measures about 5.3 km.

Under construction6 km
  1. 2023Construction start
––
  • ColasBuilder
  • GeotehnikaBuilder
–

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union21 km
    2 sections
    • Cohesion Fund, Competitiveness and Cohesion Programme 2021–2027: grant agreement signed 27 January 2026 for the whole Bjelovar – Bulinac – Velika Pisanica project (EUR 70 million from the Cohesion Fund, EUR 12.42 million national co-financing, eligible costs EUR 107.45 million; the press gives a project value of EUR 134 million). It covers this lot and the next.
    • Cohesion Fund, Competitiveness and Cohesion Programme 2021–2027: grant agreement signed 27 January 2026 for the whole Bjelovar – Bulinac – Velika Pisanica project (EUR 70 million from the Cohesion Fund, EUR 12.42 million national co-financing, eligible costs EUR 107.45 million; the press gives a project value of EUR 134 million). It covers this lot and the previous one.

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. Wikipedia (en): D10 road (Croatia) (exit list: Vrbovec 1 at km 8.0; Gradec – Križevci opened September 2016)read Oct 10, 2026
  2. Wikipedia (en): D12 road (Croatia) (Vrbovec 2 – Farkaševac opened 16 April 2019; Farkaševac at km 10.6, Bjelovar at km 27.5)read Oct 10, 2026
  3. Križevci.info: Otvorena brza cesta do Križevaca (2 September 2016; Gradec – Križevci 12.5 km, 595 million kuna; Sveta Helena – Vrbovec opened 2002, Vrbovec – Gradec 2007)read Oct 10, 2026
  4. Ministry of the Sea, Transport and Infrastructure: Otvorena novoizgrađena dionica brze ceste Vrbovec – Gradec (3 August 2007; 15.5 km, about 330 million kuna)read Oct 10, 2026
  5. Vrbovec.hr: Otvorena dionica brze ceste Vrbovec – Gradec (3 August 2007; 15.15 km, Strabag Hrvatska main contractor)read Oct 10, 2026 · archived copy
  6. Vlada RH: Otvorena brza cesta od Vrbovca do Farkaševca (16 April 2019; 10.6 km, 349 million kuna excluding VAT)read Oct 10, 2026
  7. Hrvatske ceste: DC12 section čvor Bjelovar – čvor Bulinac – čvor Velika Pisanica (stages 1A, 1B, 1C, 2A; 20.75 km; Cohesion Fund EUR 70 million; eligible costs EUR 107.45 million)read Oct 10, 2026
  8. tportal (Hina): Gradi se nova brza cesta kod Križevaca (5 October 2026; Križevci – Kloštar Vojakovački 7.5 km, Kamgrad, EUR 30.6 million excluding VAT, deadline 23 December 2026)read Oct 10, 2026
  9. Klikni.hr: Izgradnja brze ceste Bjelovar – Virovitica napreduje, ali puževim korakom (26 November 2025)read Oct 10, 2026
  10. Klikni.hr: Iako do Bjelovara brza cesta nije stigla, sad nastavlja prema Virovitici (27 January 2026)read Oct 10, 2026
  11. Forbes Hrvatska: Počela izgradnja brze ceste od Bjelovara prema Virovitici (27 January 2026; stages 1A and 1B 9.38 km, Zagorje Gradnja, 45 million euro)read Oct 10, 2026
  12. MojPortal.hr: Ministar Butković: Gradi se brza cesta do Bulinca! Dionicu do Bjelovara želimo završiti do kraja 2026 (27 January 2026)read Oct 10, 2026
  13. MojPortal.hr: Brza cesta do Bjelovara dobila građevinsku dozvolu, radovi kreću na proljeće (4 March 2022; Kamgrad and Pedom Asfalti, 30 months)read Oct 10, 2026
  14. Bjelovar.live: Brza cesta za 30 mjeseci stiže do Bjelovara (30 September 2022; Kamgrad introduced to the works, two lanes)read Oct 10, 2026
  15. Bauštela.hr: Novi produžetak za najiščekivaniju brzu cestu u Hrvatskoj (9 September 2026; Kamgrad and Pedom Asfalti contract 35.13 million euro raised to 39.82 million excluding VAT)read Oct 10, 2026
  16. Bauštela.hr: Cesta od 134 milijuna gradi se više od desetljeća (stages 1A and 1B, 9.36 km, 45.01 million euro, Zagorje gradnja and Texo molior, 30 months)read Oct 10, 2026
  17. Glas Slavonije: Radi se na glavnoj trasi i čvorištu Špišić Bukovica (19 August 2024; Virovitica – Špišić Bukovica 5.6 km, 28.9 million euro, works begun the previous year)read Oct 10, 2026
  18. Virovitičko-podravska županija: Hrvatske ceste objavile su natječaj za gradnju nove dionice brze ceste DC12 (7 April 2026; 11.37 km, estimated value 61.54 million euro)read Oct 10, 2026
  19. OpenStreetMap contributors: route geometry (ODbL), ways with ref D10 and D12read Oct 10, 2026
  20. Klikni.hr: Brza cesta do Bjelovara kasnit će više nego što smo očekivali (27 January 2026; Farkaševac – Breza begun 2020, Breza – Bjelovar 2022)read Oct 10, 2026
  21. Klikni.hr: Župan otkrio kada bi brza cesta mogla biti gotova (12 June 2026; works Virovitica – Špišić Bukovica finished, stages 1A and 1B due summer 2028)read Oct 10, 2026
  22. Grad Virovitica: Svečanom sjednicom obilježen Dan grada (August 2026; Virovitica – Špišić Bukovica section finished)read Oct 10, 2026