Zaprešić – Zabok railway modernisation and electrification (R201)

Modernisation and electrification of the 23.9 km Zaprešić – Zabok section of the R201 Zaprešić – Čakovec regional line, with rebuilt stations at Novi Dvori, Luka, Veliko Trgovišće and Zabok and new stops at Pojatno, Kupljenovo and Žeinci. The works contract with Swietelsky was signed on 12 June 2018 for €74.4 million. Works ran from July 2018 to September 2022. A second lot covers the 11 km renewal of the local line Hum-Lug – Gornja Stubica, contracted on 2 June 2026 for €16 million.

Total length
35 km
Open today
24 km
Sections
2
Cost on record
€92.497M
1 of 2 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of Zaprešić – Zabok railway modernisation and electrification (R201): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Zaprešić – Zabok

The €74.4 million is the works contract. The grant agreement is worth €102.6 million, of which €81.5 million is eligible cost; the two are different figures. The grant implementation period runs from January 2014 to December 2023. The works rebuilt the stations Novi Dvori, Luka, Veliko Trgovišće and Zabok, the stops Pojatno, Kupljenovo and Žeinci, and electrified the line, allowing passenger trains up to 120 km/h. Length measured from OpenStreetMap geometry is 23.6 km against the 23.9 km recorded by HŽ Infrastruktura; the drawn line starts about 150 m after Zaprešić station and ends at Zabok.

Opened24 km
  1. Jun 12, 2018Tender awarded
  2. Jul 2018Construction start
  3. Sep 2022Opened
–
  • European UnionOperational Programme Competitiveness and Cohesion 2014–2020 (Cohesion Fund), grant agreement KK.07.5.1.03.0001 of 9 November 2017: €69.3 million (85%) of €81.5 million in eligible costs.
  • National budgetState budget: €12.2 million (15%) of the eligible costs.
  • Swietelsky d.o.o.Builder
Contract value €74.4M
Hum-Lug – Gornja Stubica renewal

Contract signed on 2 June 2026. The €16 million covers €13 million for the track and €3 million for four bridges and three culverts. The first phase covers the track grid, drainage, stops and level crossings, with a two-year deadline; buildings, including station buildings, may follow in a second phase. A board member of Pružne građevine said works were expected to start in the autumn of 2026, so no construction start is recorded. Line speed is to rise to 80 km/h. This is the local line Zabok – Gornja Stubica (L202), a branch off R201 at Hum-Lug, not R201 itself. Length of 11 km as stated by HŽ Infrastruktura; the drawn line, measured from OpenStreetMap geometry, is 10.6 km.

Tendered11 km
  1. Jun 2, 2026Tender awarded
  2. ≈2028Expected openingProjected from contract
–
  • LoanFinanced from the €900 million agreement between the Government and the European Investment Bank for local and regional railways.
  • Pružne građevineBuilder
24 mo execution · Contract value €16M

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union24 km
    1 section
    • Operational Programme Competitiveness and Cohesion 2014–2020 (Cohesion Fund), grant agreement KK.07.5.1.03.0001 of 9 November 2017: €69.3 million (85%) of €81.5 million in eligible costs.
  • National budget24 km
    1 section
    • State budget: €12.2 million (15%) of the eligible costs.
  • Loan11 km
    1 section
    • Financed from the €900 million agreement between the Government and the European Investment Bank for local and regional railways.

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. HŽ Infrastruktura: Modernizacija i elektrifikacija pruge Zaprešić – Zabokread Oct 10, 2026
  2. HŽ Infrastruktura: Počinje obnova pruge Hum-Lug – Gornja Stubicaread Oct 10, 2026
  3. OpenStreetMap contributors (geometry of railway lines R201 and L202, ODbL)read Oct 10, 2026