Highways

M0 Budapest ring road

Budapest's ring road, drawn from the M1 interchange at Budaörs round the south, east and north to Road 11 at Békásmegyer: about 78 km open, 108 km planned. The south sector (M1 – M5) opened in 1990 and 1994 as a 2x2 road without hard shoulders, and the link from Road 51 to the M5 followed in 2013. The east sector (M5 – M3) opened in 2005 and 2008, and the north sector (M3 – Road 11) in 1999 and 2008, the latter with the Megyeri Bridge over the Danube. Lots follow the section table on hu.wikipedia, checked against NIF project pages and press releases. The 2012–2015 widening of the south sector to 2x3 lanes reworks road that was already open, so it is described in the lot notes and adds no length. The 1988 stretch between Road 51 and the M5 is now the M51 and is not part of this project. The west sector between the M1 and Road 11 is unbuilt; its two lots are drawn only where OpenStreetMap maps a proposed route.

Total length
106 km
Open today
79 km
Sections
10
Cost on record
€60.191M
1 of 10 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of M0 Budapest ring road: status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
South sector: M1 – Road 6

Chainage km 0–13.9 (M1 to Road 6), opened 3 May 1994 as a 2x2 road. Widened to 2x3 lanes in two steps: M1 km 2.84 – M6 (6.56 km, Colas Hungária Zrt., net contract HUF 11.11 billion), opened 19 June 2012, and M1 – M7 (2.725 km, Betonútépítő Zrt., net contract HUF 6.38 billion), opened 23 November 2015. The M6 – Road 51 widening of 2013 also covers the part of this lot east of the M6 junction.

Opened14 km
  1. May 3, 1994Opened
––––
South sector: Road 6 – Road 51

Chainage km 13.9–23.2, the first part of the ring that is still on the M0, opened 16 November 1990 as a 2x2 road. It includes the Deák Ferenc Bridge over the Danube (770 m) and the Soroksár bridge over the Ráckeve Danube branch (499 m). Widened to 2x3 lanes between the M6 junction and Road 51 (11.06 km, M-0 déli ág II. Konzorcium, net contract HUF 37.03 billion), opened 30 June 2013.

Opened9 km
  1. Nov 16, 1990Opened
––––
South sector: Road 51 – M5 (new alignment)

Chainage km 23.2–29.5, a new 2x3 alignment that links the older south sector to the east sector and cut the route by 4.2 km. Before it opened, the M0 ran from Road 51 to the M5 along the 1988 road that is now the M51, and the east sector began on the M5. The M51 name was applied on 31 August 2013.

Opened6 km
  1. Jul 27, 2009Tender awarded
  2. Sep 14, 2009Construction start
  3. Aug 31, 2013Opened
–
  • European UnionNIF: "A beruházást az Európai Unió és a magyar állam támogatja" (supported by the European Union and the Hungarian state); no programme or share is given.
  • EMWL Autópálya Konzorcium (EuroAszfalt Kft., Lavinamix Kft., MAHÍD 2000 Zrt., W-MIX Kft.)Builder
Contract value Ft11.8B
East sector: M5 – M4

Chainage km 29.5–42.2, opened 17 December 2005 together with the 12.5 km Vecsés–Üllő bypass of Road 4. NIF says both sections took 17 months to build and that Strabag built the section; the release gives HUF 33.8 billion and HUF 12.5 billion without saying clearly which road each covers, so no cost is recorded. hu.wikipedia says the M5 – M3 stretch has concrete pavement.

Opened13 km
  1. Dec 17, 2005Opened
––
  • STRABAG Rt.Builder
–
East sector: M4 – M3

Chainage km 42.2–68.7, opened 16 September 2008. NIF announced the start of construction on 13 March 2006 and planned completion for the end of 2007. The release names the "ED"-M0 joint venture for the stretch between Road 3 and the M3, and PVT-M0 for the second and third sub-sections (6.7 km and 10.9 km); the first sub-section is not named in the text. The client was Nemzeti Autópálya Zrt. The EUR 284 million is a budget, not an outturn, so no cost is recorded.

Opened27 km
  1. Sep 16, 2008Opened
–
  • European UnionNIF, March 2006: EU Cohesion Fund support of 85% within a EUR 284 million investment budget; the winning tenders left room for the 12 km M31 from the same budget.
  • PVT-M0 Konzorcium (Porr Technobau und Umwelt AG Magyarországi Fióktelepe, Viadom Építőipari Zrt., Teerag-Asdag AG)Builder
  • "ED"-M0 Közös VállalkozásBuilder
–
North sector: M3 – M2

Table chainage km 69.65–72.54. Opened 16 June 1999 as a 2x2 road with a median and hard shoulders, with five junctions on the M3 – Road 2 stretch. Unitef '83 made the design phases for the M3 – Road 11 sector. hu.wikipedia's M0 article gives 1998 for the M3 – Road 2 opening; the section table, which cites 1999 press, is followed here.

Opened3 km
  1. Jun 16, 1999Opened
––
  • Unitef '83Designer
–
North sector: M2 – Road 2

Table chainage km 72.54–75.6. Opened 29 October 1999 as a 2x2 road, the continuation of the M3 – M2 lot. The two lots were known as Roads 2/B and 2/A before the ring was joined up.

Opened3 km
  1. Oct 29, 1999Opened
––
  • Unitef '83Designer
–
North sector: Road 2 – Road 11 (Megyeri Bridge)

Table chainage km 72.835–76.709, opened 30 September 2008. The Megyeri Bridge between Újpest and Budakalász (km 74.526–76.387, 1861.35 m, five bridges and nine structures, designed by Unitef-Céh Kkt.) is inside this lot and is entered as its viaduct length; the consortium named is the bridge's builder. It was handed over on 30 September 2008 and went into traffic on provisional permits, built for 2 x 2 lanes with room for 2 x 3. hu.wikipedia gives HUF 63 billion as the bridge's total construction cost, with no price year or VAT basis; it covers the bridge, not the whole lot, so no cost is recorded. The drawn centreline is about 15% shorter than the tabled length: it starts at the OpenStreetMap node of the Road 2 junction and ends where the westbound carriageway ends.

Opened4 km
  1. 2006Construction start
  2. Sep 30, 2008Opened
––
  • M0 Északi Duna-híd konzorcium (Hídépítő Zrt. 60%, Strabag Építő Zrt. 40%)Builder
  • Unitef '83Designer
–
West sector: Road 11 – Road 10 (planned)

en.wikipedia: the 9 km section between Highway 11 and Highway 10 is planned but construction is not scheduled. The drawn line is OpenStreetMap's proposed route (relation "M0 északnyugati szektor Plan-A"), 7.3 km between the Road 11 end and the Road 10 crossing, so about 19% shorter than the stated length. The planning table on hu.wikipedia gives 8.040 km for the same section, against 7.346 km between its chainage points (km 76.709 and 84.055); the drawn line starts about 0.5 km west of the end of the Road 2 – Road 11 lot. hu.wikipedia says design of the west sector began in 2018 and the project came off the agenda early the next year; it also gives an estimate of nearly HUF 400 billion for the whole west sector, with no price year.

Planned9 km–––––
West sector: Road 10 – M1 (planned)

en.wikipedia: the 18 km remaining section between Highway 10 and the oldest part of the M0 at the M1 interchange. The drawn line is OpenStreetMap's proposed route (relation "M0 északnyugati szektor Plan-A"), 18.3 km from the Road 10 crossing to the end of the built M0 near the M1. The west sector is mostly tunnel and viaduct, per the junction table on hu.wikipedia (planned tunnels of 2020 m and 3190 m). It is not on the Trans-European network, so it would need national funding, according to hu.wikipedia.

Planned18 km–––––

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union33 km
    2 sections
    • NIF: "A beruházást az Európai Unió és a magyar állam támogatja" (supported by the European Union and the Hungarian state); no programme or share is given.
    • NIF, March 2006: EU Cohesion Fund support of 85% within a EUR 284 million investment budget; the winning tenders left room for the 12 km M31 from the same budget.

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. Wikipedia (hu): Magyarország autópályái, chronological table of sections (M0 rows)read Oct 10, 2026
  2. Wikipedia (hu): M0-s autóút (Magyarország)read Oct 10, 2026
  3. Wikipedia (en): M0 motorwayread Oct 10, 2026
  4. Wikipedia (hu): Megyeri hídread Oct 10, 2026
  5. NIF press release: 13 kilométerrel hosszabb az M0 körgyűrű! (17 December 2005)read Oct 10, 2026 · archived copy
  6. NIF press release: Indul az M0 keleti szektorának építése (13 March 2006)read Oct 10, 2026 · archived copy
  7. NIF project page: M0 déli szektor 51. sz. főút-M5 autópálya közötti szakasz kiépítéseread Oct 10, 2026 · archived copy
  8. NIF project page: M0 autópálya déli szektor M1-M6 autópályák közötti szakaszának bal pálya, valamint csatlakozó létesítményei kivitelezési munkáiread Oct 10, 2026 · archived copy
  9. NIF project page: M0 déli szektor bővítése az M6 AP és az 51. sz. főút közöttread Oct 10, 2026 · archived copy
  10. NIF project page: M0-M1 csomópont infrastrukturális fejlesztéseread Oct 10, 2026 · archived copy
  11. EuroAszfalt Kft.: reference M0 déli szektor 51. sz. főút – M5 autópálya közötti, 2x3 sávos szakasza (contract date, price, site handover)read Oct 10, 2026
  12. Unitef'83 Zrt.: M0 Északi szektor (design of M3 – Road 11 sector)read Oct 10, 2026
  13. OpenStreetMap: relation 21750, M0 (network HU:expressway), and ways with ref=M0read Oct 10, 2026
  14. OpenStreetMap: relation 7638705, M0 északnyugati szektor Plan-A (highway=proposed)read Oct 10, 2026
  15. OpenStreetMap contributors: route geometry (ODbL)read Oct 10, 2026

Figures last checked against their sources in Oct 10, 2026.