Highways

M44 expressway (Kecskemét – Kunszentmárton – Békéscsaba)

Expressway from the M5 at Kecskemét east to Békéscsaba, built by NIF in sections from 2017. Lots follow the opened sections: Tiszakürt – Kondoros (2019, three contract stages), Kondoros – Békéscsaba (2020), Lakitelek – Tiszakürt (2021), Szentkirály – Lakitelek (2024) and Kecskemét – Szentkirály (2025). The interchange with the M5 is under construction. Contract values come from hu.wikipedia and the investment portal and are in HUF millions; the VAT basis is given only where stated. The planned extension from Békéscsaba to the Romanian border is not recorded.

Total length
126 km
Open today
124 km
Under construction
2 km
Sections
8
Cost on record
€1.4B
6 of 8 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of M44 expressway (Kecskemét – Kunszentmárton – Békéscsaba): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Kecskemét (M5 interchange – road 5)

Second stage of the Kecskemét–Szentkirály section: a full cloverleaf interchange where the M44 meets the M5, plus 1.8 km of 2x2 expressway. Until it opens the M44 and M5 connect only towards Budapest at the Kecskemét-Centrum junction. The investment portal gives construction start 13 May 2024, a completion deadline of 28 February 2027 and a net contract sum of HUF 41,981,774,352. The contract date is not given, so the figure has no price year and no award revision is recorded. The drawn length covers only the mapped construction ways and is shorter than the sourced 1.8 km.

Under construction2 km
  1. May 13, 2024Construction start
  2. Feb 28, 2027Expected opening
––
  • Hódút Építő Kft.Builder
Contract value Ft42B
Kecskemét – Szentkirály

First stage: 32.3 km of 2x2 expressway without hard shoulder from road 5 at Kecskemét to Szentkirály, with a junction at road 441. The notice of 6 June 2021 gave 32.2 km and 14 structures. Hódút Kft. won at HUF 106.996 billion (announced January 2022; net or gross not stated). Works officially began on 30 March 2022 and the section opened on 15 April 2025. It runs on the alignment first planned as the M8.

Opened32 km
  1. Jan 2022Tender awarded
  2. Mar 30, 2022Construction start
  3. Apr 15, 2025Opened
––
  • Hódút Kft.Builder
Contract value Ft107B
Szentkirály – Lakitelek

4.6 km of 2x2 expressway without hard shoulder. The design-build contract with Közgép (HUF 35.49 billion) also covers the 4623 side-road renewal, a 3.5 km Szentkirály bypass, the 4622 side-road renewal, a roundabout and 3.4 km of road 44, so it is not the cost of the expressway alone. A second Közgép contract of HUF 8.12 billion covers 20.3 km of road 44 and is not recorded here. Design and build began in February 2020 (month only given) and the section opened on 7 May 2024. The contract date is not given, so the figure has no price year and no award revision is recorded.

Opened5 km
  1. Feb 2020Construction start
  2. May 7, 2024Opened
––
  • Közgép Építő- és Fémszerkezetgyártó Zrt.Builder
Contract value Ft35.5B
Lakitelek – Tiszakürt (with the Tisza bridge)

9.9 km including the new Tisza bridge (552 m), opened in two parts: 6.7 km, with the bridge, on 15 December 2021 and 3.2 km on 21 September 2021 (from the Tiszakürt / Tiszaug junction to the temporary end of the Tiszakürt – Kondoros section). The award is dated by press reports of 28 April 2018 that named Duna Aszfalt at HUF 51.3 billion. The NIF page gives construction start July 2018 and a contract sum of HUF 51,308,917,861 (VAT basis not stated). The boundary with the next lot is placed by the sourced length of 9.9 km along the drawn line, not at the mapped Tiszakürt junction.

Opened10 km
  1. Apr 28, 2018Tender awarded
  2. Jul 2018Construction start
  3. Dec 15, 2021Opened
––
  • Duna Aszfalt Kft.Builder
Contract value Ft51.3B
Tiszakürt – Kunszentmárton

First of three construction stages of the 61.2 km Tiszakürt – Kondoros section (opened 2 October 2019): Duna Aszfalt – Hódút consortium, HUF 56.5 billion. The three stages were tendered together (result announced 15 November 2016, contracts signed December 2016, foundation stone 21 December 2016, works from early 2017). The sources give no stage lengths. Length measured from OpenStreetMap geometry between the end of the Lakitelek – Tiszakürt lot (placed by its sourced length) and the Kunszentmárton junction. The three stage lengths sum to 59.4 km against 61.2 km sourced for the section.

Opened9 km
  1. Nov 15, 2016Tender awarded
  2. 2017Construction start
  3. Oct 2, 2019Opened
––
  • Duna Aszfalt Kft.Builder
  • Hódút Kft.Builder
Contract value Ft56.5B
Kunszentmárton – Csabacsűd

Second stage of the Tiszakürt – Kondoros section (opened 2 October 2019): EuroAszfalt – Swietelsky – Soltút – A-Híd consortium, HUF 43.98 billion. Includes the 450 m Berkó Dezső bridge over the Hármas-Körös. Length measured from OpenStreetMap geometry, cut at the Kunszentmárton and Kardos / Csabacsűd junctions.

Opened34 km
  1. Nov 15, 2016Tender awarded
  2. 2017Construction start
  3. Oct 2, 2019Opened
––
  • EuroAszfalt Építő és Szolgáltató Kft.Builder
  • Swietelsky Magyarország Kft.Builder
  • Soltút Kft.Builder
  • A-Híd Zrt.Builder
Contract value Ft44B
Csabacsűd – Kondoros

Third stage of the Tiszakürt – Kondoros section (opened 2 October 2019): Duna Aszfalt – Hódút consortium, HUF 45.2 billion. The sources give no stage lengths. Length measured from OpenStreetMap geometry between the Kardos / Csabacsűd junction and the start of the Kondoros – Békéscsaba lot, which is placed by that lot's sourced length of 17.6 km (the section ends east of the mapped Kondoros junction).

Opened16 km
  1. Nov 15, 2016Tender awarded
  2. 2017Construction start
  3. Oct 2, 2019Opened
––
  • Duna Aszfalt Kft.Builder
  • Hódút Kft.Builder
Contract value Ft45.2B
Kondoros – Békéscsaba

17.6 km with one grade-separated junction (Békéscsaba-nyugat / Kétsoprony). The site was handed over in mid-February 2018 (month only recorded) and the section opened on 11 December 2020, 1.5 months before the 31 January 2021 deadline. Duna Aszfalt was named winner on 25 October 2017 at HUF 41.4 billion. Boundary placed by the sourced length: the start is 17.6 km before the end of the drawn line, east of the mapped Kondoros junction.

Opened18 km
  1. Oct 25, 2017Tender awarded
  2. Feb 2018Construction start
  3. Dec 11, 2020Opened
––
  • Duna Aszfalt Kft.Builder
Contract value Ft41.4B

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Related projects

Sources

  1. Wikipedia (hu): M44-es autóút (Magyarország), sections, contractors, contract values, opening datesread Oct 10, 2026
  2. NIF: Békéscsaba megközelítése, M44 Lakitelek – Tiszakürt (9.9 km, construction start July 2018, contract sum HUF 51,308,917,861)read Oct 10, 2026 · archived copy
  3. Beruházási portál: Békéscsaba megközelítése, M44 Kecskemét–Szentkirály II. ütem (net contract sum HUF 41,981,774,352; start 13 May 2024; deadline 28 February 2027)read Oct 10, 2026
  4. OpenStreetMap: ways with ref M44 (highway=trunk, highway=construction), cut at motorway_junction nodesread Oct 10, 2026
  5. OpenStreetMap contributors: route geometry (ODbL)read Oct 10, 2026

Figures last checked against their sources in Oct 10, 2026.