Railway line 202 Gdynia Chylonia – Słupsk (modernisation)
Modernisation of railway line 202 between Gdynia Chylonia and Słupsk, split at Lębork. The contracted Gdynia Chylonia – Lębork section adds tracks and upgrades the existing line. Works on Lębork – Słupsk are under way, including a second track. PLK's works at Słupsk station are a separate contract and are not mapped as a separate lot.
- Total length
- 110 km
- Open today
- 0 km
- Under construction
- 54 km
- Sections
- 2
- Cost on record
- €617.402M
- 1 of 2 sections carry a comparable figure
Restated into EUR at 2025 prices.
Sections
| Sections | Status | Length | Timeline | Cost | Funding | Contractors | Contract terms |
|---|---|---|---|---|---|---|---|
| Gdynia Chylonia – Lębork The works contract covers the existing line from Gdynia Chylonia to Lębork. PLK describes 55 km of track works. Its 2026/2027 track-closure schedule gives the section as km 25.200–81.150, a 55.95 km chainage span; the sourced chainage is used. The package adds a second track between Gdynia Chylonia and Rumia and between Wejherowo and Lębork, plus two suburban tracks between Rumia and Wejherowo. PLK planned completion in 2029; ZUE states a contract duration of 56 months. The OSM line drawn is 53.4 km, about 5% shorter than the chainage span, so the sourced length is kept. | Tendered | 56 km |
| – | – |
| 56 mo execution · Contract value zł2.6B |
| Lębork – Słupsk CUPT gives the line 202 works as km 81.150–135.100, 53.950 km, and states that the completed line will be double track. PLK reported construction under way on the Lębork – Słupsk section in July 2025 and named Intercor as the contractor. Works at Słupsk station are a separate PLK contract with Torpol and are not split into another mapped lot. The OSM line drawn is 51.2 km, about 5% shorter than the sourced chainage, which is kept. No award date for the Intercor package was found, so its contract value is not recorded. | Under construction | 54 km |
| – | – |
| – |
Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.
Related projects
- HighwaysA1 motorway (Rusocin – Toruń – Łódź – Częstochowa – Gliwice – Gorzyczki)Same contractor: Intercor
- HighwaysA2 motorway (Świecko – Poznań – Łódź – Warszawa – Siedlce – Biała Podlaska – Kukuryki)Same contractor: Intercor
- RailwaysCentralna Magistrala Kolejowa (line 4 Grodzisk Mazowiecki – Zawiercie)Same contractor: ZUE
- RailwaysRail Baltica in Poland: Warszawa Rembertów – Sadowne – Czyżew – Białystok – Ełk (lines 449, 6 and 38, E75)Same contractor: Intercor
- RailwaysRailway line 8 Warszawa – Radom – Kielce – Kraków (modernisation)Same contractor: ZUE
- HighwaysS10 expressway (Szczecin – Stargard – Wałcz – Piła – Bydgoszcz – Toruń – Płońsk)Same contractor: Intercor
Sources
- PKP PLK: Miliardy na lepszą kolej z Trójmiasta do Słupska (16.12.2025)read Oct 13, 2026
- ZUE S.A. current report 36/2025: Gdynia Chylonia – Lębork contract (16.12.2025)read Oct 13, 2026
- PKP PLK: Kolej w Słupsku zyskuje nowe oblicze (31.07.2025)read Oct 13, 2026
- CUPT: Umowa FEnIKS, Prace na linii kolejowej nr 202 na odcinku Gdynia Chylonia – Słupsk – faza IIread Oct 13, 2026
- PKP PLK: Sieciowy harmonogram zamknięć torowych, rozkład jazdy 2026/2027read Oct 13, 2026
- OpenStreetMap relation 2345694: railway line 202 Gdańsk Główny – Stargard, route geometry (ODbL)read Oct 13, 2026
- OpenStreetMap contributors: copyright and ODbL attributionread Oct 13, 2026
Figures last checked against their sources in Oct 13, 2026.