S10 expressway (Szczecin – Stargard – Wałcz – Piła – Bydgoszcz – Toruń – Płońsk)
East–west expressway from Szczecin towards the S50 Warsaw ring near Nacpolsk, built in sections. Lots follow the GDDKiA contract sections, grouped by contract, and are cut at junctions mapped in OpenStreetMap; where a junction is not mapped, the lot note says how the cut was placed. Not drawn: the Piła Północ – Piła Wschód common run with S11 and the Piła Wschód – Wyrzysk Zachód section (planned, no mapped way and no contract), the Bydgoszcz Zachód – Bydgoszcz Błonie stretch common with S5 (opened on 31 December 2020, drawn in pl-s5), the Toruń Południe – Włocławek Północ stretch that is the A1 (not designated S10), and the planned Włocławek Północ – Nacpolsk section. Contract values come from the GDDKiA contract table of October 2026 and include VAT; older figures come from pl.wikipedia and say where the VAT basis is not stated.
- Total length
- 267 km
- Open today
- 76 km
- Under construction
- 124 km
- Sections
- 20
- Cost on record
- €1.5B
- 12 of 20 sections carry a comparable figure
Restated into EUR at 2025 prices.
Sections
| Sections | Status | Length | Timeline | Cost | Funding | Contractors | Contract terms |
|---|---|---|---|---|---|---|---|
| Szczecin Kijewo – Szczecin Zdunowo (Płonia bypass) New 4.35 km section north of the Płonia district, with a 130 m bridge over the Płonia and the Szczecin Płonia and Szczecin Zdunowo junctions. The environmental decision was issued on 16 December 2022 and the ZRID permit on 26 May 2026. The first bid, from NDI at PLN 187.34 million, was set aside after a court ruling in October 2024 (pl.wikipedia). The contractor has had access to the site since 8 June 2026; the contract table gives no works start date, so the access date is recorded. The drawn line covers only the section mapped in OpenStreetMap, from the Płonia junction to Zdunowo, so it is shorter than the recorded length. | Under construction | 4 km |
| – | – |
| Contract value zł204.06M |
| Szczecin Zdunowo – Kobylanka Outbound stretch of the former DK10 from Szczecin, rebuilt in 2002–2004 as a dual carriageway. Contract date, opening date and builder come from the section table of pl.wikipedia. The article gives 5.3 km in that table and 6 km in its text. GDDKiA gave it S10 expressway designation after 28 November 2020. | Opened | 5 km |
| – | – |
| – |
| Kobylanka – Stargard Zachód (Kobylanka, Morzyczyn and Zieleniewo bypass) The first carriageway opened on 14 September 2007. The second was built by Strabag under a design-build contract signed on 12 September 2017 (PLN 57.22 million including VAT, which also covers a 3.2 km service road) and opened on 28 November 2020. The date of the contract with NCC, the length and both opening dates come from the section table of pl.wikipedia, which gives 8.8 km for the first carriageway with its junctions in a footnote. | Opened | 8 km |
| – | – |
| – |
| Stargard Zachód – Stargard Wschód (Stargard bypass) Dual-carriageway bypass of Stargard with the Stargard Zachód, Stargard Południe and Stargard Wschód junctions. It was first planned as a single carriageway and widened to a full profile after a tyre factory was sited in the town. Built by a consortium of Johann Bunte and Berger Bau. The article gives 13.4 km in the section table and 13.52 km in its text; the first figure is kept. | Opened | 13 km |
|
| – |
| – |
| Stargard Wschód – Suchań Design-build contract on the new S10 Szczecin – Piła route. ZRID permit issued on 9 December 2025. The best offer was chosen on 13 March 2024 (PLN 450.38 million, against a GDDKiA budget of PLN 562.6 million, pl.wikipedia). The drawn line is 5% longer than the recorded length. | Under construction | 14 km |
| – | – |
| Contract value zł450.39M |
| Suchań – Recz Design-build contract on the new S10 Szczecin – Piła route. ZRID permit issued on 9 December 2025. Built by a consortium of Kobylarnia (leader) and Mirbud. The drawn line is 12% shorter than the recorded length; the recorded length is kept. | Under construction | 20 km |
| – | – |
| Contract value zł667.52M |
| Recz – Cybowo Design-build contract on the new S10 Szczecin – Piła route. ZRID permit issued on 20 April 2026. Built by a consortium of Kobylarnia and Mirbud. The drawn line is 9% longer than the recorded length, which excludes both junctions; the recorded length is kept. | Under construction | 16 km |
| – | – |
| Contract value zł647M |
| Cybowo – Łowicz Wałecki (including the Kalisz Pomorski bypass) Design-build contract on the new S10 Szczecin – Piła route. ZRID permit issued on 6 February 2026. The section has 16 structures, including five road overpasses and seven wildlife underpasses (pl.wikipedia). | Under construction | 17 km |
| – | – |
| Contract value zł592.97M |
| Łowicz Wałecki – Piecnik (including the Mirosławiec bypass) Design-build contract on the new S10 Szczecin – Piła route. ZRID permit issued on 29 June 2026; the contract site reports the construction site handed to the contractor after the permit (post of 1 July 2026, no handover date given). The contract table gives no works start date, so the lot is recorded as awarded and not yet under construction. The contract completion date is 31 July 2028 in the GDDKiA contract table. | Tendered | 15 km |
| – | – |
| Contract value zł538.05M |
| Piecnik – Wałcz Zachód Design-build contract on the new S10 Szczecin – Piła route. ZRID permit issued on 20 January 2026. The works start date is from the GDDKiA contract table; the contract site gives 29 January 2026 (site handed over on 28 January). The route leaves the DK10 north of the existing road and rejoins it east of Piława at the Wałcz Zachód junction. pl.wikipedia gives 16.0 km for the section; the GDDKiA page figure is kept. | Under construction | 15 km |
| – | – |
| Contract value zł552.22M |
| Wałcz bypass (Wałcz Zachód – Witankowo) The original contract with Energopol Szczecin (PLN 430.49 million including VAT; the GDDKiA table shows its completion date moved from 18 June 2018 to 26 May 2019) was terminated on 14 October 2019 with the work unfinished. The remaining work was split among Budimex, Porr and Pol-Dróg Drawsko Pomorskie in 2020. The GDDKiA page gives PLN 583.01 million for all works contracts together; VAT basis not stated on the source page. The page gives the bypass as km 0+020 to 17+805. The drawn line runs between the Wałcz Zachód and Witankowo junction nodes mapped in OpenStreetMap and is 14% shorter than the sourced 17.83 km; the sourced length is kept. | Opened | 18 km |
| – |
|
| Contract value zł430.49M |
| Wałcz Witankowo – Piła Północ Design-build contract; the ZRID permit application was filed on 5 May 2025 and the GDDKiA page records no decision. The works start date is not stated, so the lot is recorded as awarded and not yet under construction. The line is drawn from ways mapped in OpenStreetMap as proposed. The Piła Północ junction is not mapped by name, so the end of the line is placed by the sourced length of 13.5 km, measured from the Witankowo junction. | Tendered | 14 km |
| – | – |
| Contract value zł721.3M |
| Wyrzysk bypass (Łobżenica – Wyrzysk) Single-carriageway northern bypass of Wyrzysk, with two carriageways only at the Łobżenica and Wyrzysk junctions. A second carriageway is under a design-build contract with Mirbud, signed on 21 July 2025 (PLN 121.30 million; the GDDKiA page gives 5 km, 2027–2029, and the ZRID application was filed on 21 May 2026). It is not a separate lot, so the length is not counted twice. The drawn line follows the mapped trunk ways from the western end of the Łobżenica junction to the eastern end of the Wyrzysk junction and is 17% shorter than the sourced 7.8 km; the sourced length is kept. | Opened | 8 km |
| – | – |
| – |
| Wyrzysk Wschód – Nakło nad Notecią Design-build tender announced on 9 December 2025; the GDDKiA page gives planned works for 2028–2031 and no contractor. The corridor study contract dates from 11 October 2010 and the environmental decision from 29 November 2022. The line is drawn from ways mapped in OpenStreetMap as proposed; the Nakło nad Notecią junction is placed at the proposed junction on those ways. pl.wikipedia swaps the lengths of this section and the next (20.2 and 19.5 km); the GDDKiA page figures are used. | Tendered | 20 km | – | – | – | – | – |
| Nakło nad Notecią – Bydgoszcz Zachód Design-build tender announced on 17 December 2025; the GDDKiA page gives planned works for 2028–2031 and no contractor. It includes the Ślesin and Kruszyn (Sicienko) junctions, a pair of rest areas at Strzelewo and 22 structures, and the ramps of the Bydgoszcz Zachód junction are to be rebuilt. The line is drawn from ways mapped in OpenStreetMap as proposed, from the proposed Nakło nad Notecią junction to where those ways meet S5, and is 8% longer than the recorded length. | Tendered | 20 km | – | – | – | – | – |
| Bydgoszcz Błonie – Bydgoszcz Południe (southern Bydgoszcz bypass) Part of the southern Bydgoszcz bypass, opened as a dual carriageway on 18 December 2009. The GDDKiA page gives 12 km and lists pavement rebuilding on DK5, DK10 and DW223 next to the junctions in its scope; pl.wikipedia gives 9.1 km in its section table and 12 km in its text. The drawn line runs between the Bydgoszcz Błonie and Bydgoszcz Południe junction nodes and is 19% shorter than 12 km; the sourced length is kept. The 7.2 km stretch from Bydgoszcz Zachód to Bydgoszcz Błonie, opened on 31 December 2020, is common with S5 and is drawn in the pl-s5 project (lot Bydgoszcz Opławiec – Bydgoszcz Błonie), so it is not drawn again here. | Opened | 12 km |
| – | – |
| – |
| Bydgoszcz Południe – Bydgoszcz Park Przemysłowy (with the DK25 rebuild) First of four contracts of the S10 Bydgoszcz – Toruń project. The GDDKiA page gives 8.9 km of S10 plus 5.4 km of rebuilt DK25, which is not counted here; the ZRID permit was issued on 30 October 2024. The contract completion date of 24 August 2026 has passed. The contract site reported earthworks, drainage and base-course work on 7 October 2026 and no new completion date, so no expected opening is recorded. The line is drawn from ways mapped in OpenStreetMap as under construction, from the east side of the Bydgoszcz Południe junction to where the ways change from 'odcinek 1' to 'odcinek 2'; it is 6% shorter than the recorded length. | Under construction | 9 km |
| – | – |
| Contract value zł410.82M |
| Bydgoszcz Park Przemysłowy – Solec Kujawski Second contract of the S10 Bydgoszcz – Toruń project, including the Makowiska road maintenance depot (OUD); the ZRID permit was issued on 17 June 2025. The contract table gives a completion date of 2 August 2026, moved to 17 July 2027 after annexes; the later date is recorded as the expected opening. pl.wikipedia gives 15.3 km for this section, the GDDKiA page 8.6 km. The line is drawn from ways mapped in OpenStreetMap as under construction: the western end is where the ways change from 'odcinek 1' to 'odcinek 2', the eastern end where the named 'Solec Kujawski-Toruń' ways begin. | Under construction | 9 km |
| – | – |
| Contract value zł239.84M |
| Solec Kujawski – Toruń Zachód Third contract of the S10 Bydgoszcz – Toruń project, built by a consortium of Kobylarnia (leader) and Mirbud; the ZRID permit was issued on 12 February 2025 and the GDDKiA page gives completion in the third quarter of 2026. The contract table gives a completion date of 24 April 2026, moved to 15 April 2027 after annexes; the later date is recorded as the expected opening. The line is drawn from ways mapped in OpenStreetMap as under construction, from where the named 'Solec Kujawski-Toruń' ways begin to the start of the Toruń Zachód junction ways. | Under construction | 21 km |
| – |
|
| Contract value zł425.87M |
| Toruń Zachód – Toruń Południe (southern Toruń bypass) Single-carriageway southern bypass of Toruń (the "Trasa Poligonowa", formerly Nieszawka – Czerniewice) with a reserve strip for a second carriageway. It is being rebuilt to a dual carriageway under a design-build contract with Rubau Polska (leader) and Poltores, signed on 20 January 2023 (PLN 339.95 million including VAT; works start 20 April 2026, contract completion 20 March 2027; ZRID permit issued on 31 March 2026; the GDDKiA page gives 11.9 km and adds the Toruń Podgórz and Toruń Czerniewice junctions). That upgrade is not a separate lot, so the length is not counted twice. The length of 11.8 km is from the pl.wikipedia section table; the article text gives 11.3 km. | Opened | 12 km |
| – | – |
| – |
Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.
Funding
- European Union39 km2 sections
- Co-financed under the Infrastructure and Environment Operating Programme 2014–2020 (grant PLN 264.87 million, GDDKiA page).
- The GDDKiA page gives co-financing of PLN 750 million from the Infrastructure, Climate, Environment programme (FEnIKS) for the S10 Bydgoszcz – Toruń project. The contract site says the funded project covers sections 3 and 4, with a total value of PLN 2,170 million.
A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.
Related projects
- HighwaysS6 expressway (Goleniów – Koszalin – Słupsk – Gdynia, Trasa Kaszubska)Same contractor: Budimex, Intercor, Kobylarnia, Mirbud, Mosty Łódź, Polaqua, Porr, Strabag, Wakoz
- HighwaysS3 expressway (Świnoujście – Szczecin – Zielona Góra – Legnica – Lubawka)Same contractor: Berger Bau, Budimex, Energopol Szczecin, Hermann Kirchner, Mosty Łódź, Polaqua, Porr, Strabag
- HighwaysA1 motorway (Rusocin – Toruń – Łódź – Częstochowa – Gliwice – Gorzyczki)Same contractor: Berger Bau, Budimex, Intercor, Kobylarnia, Mirbud, Polaqua, Strabag
- HighwaysS7 expressway (Gdańsk – Elbląg – Warszawa – Radom – Kielce – Kraków – Rabka)Same contractor: Budimex, Intercor, Mosty Łódź, Polaqua, Porr, Strabag, Wakoz
- HighwaysS19 expressway, Via Carpatia (Kuźnica – Białystok – Lublin – Rzeszów – Barwinek)Same contractor: Budimex, Intercor, Mosty Łódź, Polaqua, Porr, Strabag
- HighwaysS5 expressway (Nowe Marzy – Bydgoszcz – Gniezno – Poznań – Wrocław)Same contractor: Budimex, Intercor, Kobylarnia, Mirbud, Polaqua, Strabag
Sources
- Wikipedia (pl): Droga ekspresowa S10 (Polska)read Oct 10, 2026
- GDDKiA: Bieżąca realizacja PBDK, stan na październik 2026 (contract table, PDF)read Oct 10, 2026
- GDDKiA Mapa Stanu Budowy Dróg: S10 Szczecin Kijewo (bez węzła) – Szczecin Zdunoworead Oct 10, 2026
- GDDKiA Mapa Stanu Budowy Dróg: S10 Stargard Wschód – Suchańread Oct 10, 2026
- GDDKiA Mapa Stanu Budowy Dróg: S10 Suchań – Reczread Oct 10, 2026
- GDDKiA Mapa Stanu Budowy Dróg: S10 Recz – Cyboworead Oct 10, 2026
- GDDKiA Mapa Stanu Budowy Dróg: S10 Cybowo – Łowicz Wałeckiread Oct 10, 2026
- GDDKiA Mapa Stanu Budowy Dróg: S10 Łowicz Wałecki – Piecnikread Oct 10, 2026
- GDDKiA Mapa Stanu Budowy Dróg: S10 Piecnik – Wałcz Zachódread Oct 10, 2026
- GDDKiA Mapa Stanu Budowy Dróg: S10 obwodnica Wałczaread Oct 10, 2026
- GDDKiA Mapa Stanu Budowy Dróg: S10 Wałcz Witankowo (bez węzła) – Piła Północread Oct 10, 2026
- GDDKiA Mapa Stanu Budowy Dróg: S10 obwodnica Wyrzyska, dobudowa drugiej jezdniread Oct 10, 2026
- GDDKiA Mapa Stanu Budowy Dróg: S10 Wyrzysk – Nakło nad Noteciąread Oct 10, 2026
- GDDKiA Mapa Stanu Budowy Dróg: S10 Nakło nad Notecią – Bydgoszcz Zachódread Oct 10, 2026
- GDDKiA Mapa Stanu Budowy Dróg: S10 Bydgoszcz Południe – Bydgoszcz Błonieread Oct 10, 2026
- GDDKiA Mapa Stanu Budowy Dróg: S10 Bydgoszcz Południe – Bydgoszcz Park Przemysłowy wraz z rozbudową DK25read Oct 10, 2026
- GDDKiA Mapa Stanu Budowy Dróg: S10 Bydgoszcz Park Przemysłowy – Solec Kuj.read Oct 10, 2026
- GDDKiA Mapa Stanu Budowy Dróg: S10 Solec Kuj. – Toruń Zachódread Oct 10, 2026
- GDDKiA Mapa Stanu Budowy Dróg: S10 Toruń Zachód – Toruń Południeread Oct 10, 2026
- OpenStreetMap: ways tagged ref=S10 (Overpass query; e.g. way 161925774)read Oct 10, 2026
- OpenStreetMap contributors (ODbL)read Oct 10, 2026
- GDDKiA contract site S10 Kijewo – Zdunowo: Przekazanie prawa dostępu do placu budowy (9 June 2026)read Oct 10, 2026
- GDDKiA contract site S10 Łowicz Wałecki – Piecnik: Uzyskanie Decyzji ZRID i przekazanie Placu Budowy Wykonawcy (1 July 2026)read Oct 10, 2026
- GDDKiA contract site S10 Piecnik – Wałcz: Rozpoczęcie Robót (11 March 2026)read Oct 10, 2026
- S10 Bydgoszcz – Toruń, odcinek 1 contract site: Stan prac (7 October 2026)read Oct 10, 2026
- S10 Bydgoszcz – Toruń, sections 3 and 4 contract site (project data)read Oct 10, 2026
Figures last checked against their sources in Oct 10, 2026.