Railway line 8 Warszawa – Radom – Kielce – Kraków (modernisation)

PKP PLK line no. 8, 317.164 km from Warszawa Zachodnia to Kraków Główny, electrified at 3 kV DC. The lots are the modernisation contracts with a sourced extent and a signing date: Warszawa Okęcie – Czachówek Południowy, Czachówek Południowy – Warka, Warka – Radom (second track), Skarżysko-Kamienna – Tumlin and Sędziszów – Kozłów. Other works on the line are not drawn: Skarżysko-Kamienna – Suchedniów (ZUE, signed 2016), Radom – Skarżysko-Kamienna (revitalised 2011–2013 per pl.wikipedia), Tumlin – Sędziszów and Tunel – Kraków. Contract values come from press reports of the signings and do not include later annexes.

Total length
136 km
Open today
93 km
Under construction
11 km
Sections
5
Cost on record
€628.385M
5 of 5 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of Railway line 8 Warszawa – Radom – Kielce – Kraków (modernisation): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Warszawa Okęcie – Czachówek Południowy

Modernisation of 27 km with rebuilt platforms and track layout, design and build, for up to 160 km/h; 77 km of track and 101 switches were to be replaced (PLK, 2016). The signing release gives 462 million PLN and a duration of 20 months; a PLK release of February 2016 gives 460 million PLN. The line was originally due to be modernised by 2012. In December 2016 PLK planned to finish the whole investment in the third quarter of 2017; the date trains began using the finished stretch was not found, so the opened date is the day trains ran on two tracks along the whole Warszawa – Radom route (29 August 2021), and the stretch may have opened earlier. Passenger speeds on the modernised line Okęcie – Radom Główny rose to 160 km/h from 11 June 2023. The drawn centreline is 7% shorter than the sourced 27 km; the sourced length is kept.

Opened27 km
  1. Jul 27, 2015Tender awarded
  2. Aug 29, 2021Opened
–
  • European UnionPhase II of Warszawa Okęcie – Radom (LOTs A, B, F) as a whole, under the Infrastructure and Environment Operational Programme 2014–2020: total investment EUR 312,259,480, Cohesion Fund contribution EUR 171,847,828. The figure also covers the Czachówek Południowy – Warka lot. The EC page gives a project duration of 01/2013 – 06/2021.
  • Trakcja PRKiIBuilder
Contract value zł462M
Czachówek Południowy – Warka

Design and build for 19.3 km: two tracks from Czachówek Południowy to Warka, level crossings, and the Warka and Chynów stations. The planned completion date given at signing was November 2020. PLK later gave this lot and Warka – Radom together as over 645 million PLN net (10 March 2022). The date trains began using this stretch was not found; the opened date is the day trains ran on two tracks along the whole Warszawa – Radom route (29 August 2021), and the stretch may have opened earlier. The Warka Miasto stop opened on 13 March 2022. Part of phase II (LOTs A, B, F), see the funding entry on the Okęcie lot. The drawn centreline is within 2% of the sourced length.

Opened19 km
  1. Apr 11, 2017Tender awarded
  2. Aug 29, 2021Opened
––
  • StrabagBuilder
  • ZUEBuilder
  • BudimexBuilder
Contract value zł216.7M
Warka – Radom (second track)

Design and build including a second track between Warka and Radom, with traffic suspended for about half a year; construction was to take about 2.5 years after design. Two tracks ran from Warka to Dobieszyn from 14 March 2021 and along the whole route from 29 August 2021. Passenger speeds on the modernised line Okęcie – Radom Główny rose to 160 km/h from 11 June 2023. The report puts the whole Okęcie – Radom modernisation at about 1.8 billion PLN; PLK gave about 1.7 billion PLN in June 2023. Length is the difference of the Warka (km 56.444) and Radom Główny (km 102.944) chainages on pl.wikipedia; the drawn centreline is 46.5 km.

Opened47 km
  1. Apr 11, 2017Tender awarded
  2. Aug 29, 2021Opened
––
  • Swietelsky RailBuilder
  • Track TecBuilder
  • InfrakolBuilder
  • Leonhard WeissBuilder
  • IntopBuilder
Contract value zł429M
Skarżysko-Kamienna – Tumlin

Design and build of two tasks: LOT-A1-1 Skarżysko-Kamienna – Łączna (km 142.820 to 161.810) and LOT-A1-2 Łączna (without the station) – Tumlin (km 161.810 to 175.001), excluding Tumlin station; part of the project "Prace na linii kolejowej nr 8 na odcinku Skarżysko-Kamienna – Kielce – Kozłów". The contractor has 36 months for construction. The scope includes over 62 km of track, new platforms at Suchedniów, Łączna and Zagnańsk, 13 level crossing upgrades and a road tunnel at Suchedniów. Passenger trains are to reach 120 km/h and freight 100 km/h; PLK states that speeds rise by the end of 2028. No construction start was found. The drawn centreline is 2% shorter than the km span.

Tendered32 km
  1. Feb 6, 2025Tender awarded
  2. 2028Expected opening
––
  • Przedsiębiorstwo Napraw i Utrzymania Infrastruktury Kolejowej w Krakowie (PNUiK)Builder
Contract value zł678M
Sędziszów – Kozłów

Design and build of about 11 km on the Świętokrzyskie – Małopolskie border (LOT B2_2 and B3 of Sitkówka Nowiny – Kozłów), excluding Sędziszów station. Line speed rises from 110 to 140 km/h (160 km/h beyond the Kozłów exit head), freight from 80 to 120 km/h. The tender was launched on 4 January 2023; 13 bids were opened on 31 July 2023. According to the schedule the modernisation is to end in June 2027; PLK (16 April 2025) gives "over 300 million PLN" for the 11 km, with the Kozłów station and the Klimontów stop, ready in 2027. The contract date is that of the report (12 July 2024). The drawn centreline is 10% longer than the sourced approximate 11 km (it runs to the Kozłów exit head); the sourced length is kept.

Under construction11 km
  1. Jul 12, 2024Tender awarded
  2. Nov 2024Construction start
  3. Jun 2027Expected opening
––
  • Pomorskie Przedsiębiorstwo Mechaniczno-Torowe (PPM-T)Builder
Contract value zł287.66M

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union27 km
    1 section
    • Phase II of Warszawa Okęcie – Radom (LOTs A, B, F) as a whole, under the Infrastructure and Environment Operational Programme 2014–2020: total investment EUR 312,259,480, Cohesion Fund contribution EUR 171,847,828. The figure also covers the Czachówek Południowy – Warka lot. The EC page gives a project duration of 01/2013 – 06/2021.

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. Wikipedia (pl): Linia kolejowa nr 8read Oct 10, 2026
  2. Rusza modernizacja kolejnego odcinka ósemkiread Oct 10, 2026
  3. PKP PLK z umowami na modernizację Warka – Radomread Oct 10, 2026
  4. Modernizacja linii kolejowej nr 8 Warszawa-Radomread Oct 10, 2026
  5. Linia 8: Sędziszów – Kozłów nareszcie z umowąread Oct 10, 2026
  6. European Commission: Modernizacja linii kolejowej nr 8, odcinek Warszawa Okęcie–Radom (LOT A, B, F), faza IIread Oct 10, 2026
  7. OpenStreetMap: relation 318914, Linia kolejowa nr 8 Warszawa Zachodnia – Kraków Główny (geometry, ODbL)read Oct 10, 2026
  8. OpenStreetMap contributors: route geometry (ODbL)read Oct 10, 2026
  9. Rusza modernizacja pierwszego odcinka linii Warszawa – Radomread Oct 10, 2026
  10. Warszawa Okęcie – Czachówek: dobre tempo prac, od marca kolejny etap przebudowyread Oct 10, 2026
  11. W Piasecznie od grudnia z nowego peronuread Oct 10, 2026
  12. Warka – Radom, dwutorowo jedziemy do Dobieszynaread Oct 10, 2026
  13. Od niedzieli w Radomiu jedziemy z nowych przystankówread Oct 10, 2026
  14. Warka Miasto – nowy przystanek lepszy dostęp do koleiread Oct 10, 2026
  15. Krótsze podróże pociągami między Radomiem a Warszawąread Oct 10, 2026
  16. Nowoczesna kolej ze Skarżyska-Kamiennej w kierunku Kielcread Oct 10, 2026
  17. Zmodernizujemy najważniejszą linię kolejową w województwie świętokrzyskimread Oct 10, 2026

Figures last checked against their sources in Oct 10, 2026.