S61 expressway Via Baltica (Ostrów Mazowiecka – Łomża – Ełk – Suwałki – Budzisko)

The Polish part of the Via Baltica (E67), from the Podborze junction on the S8 near Ostrów Mazowiecka to the Lithuanian border at Budzisko, drawn as one centreline from OpenStreetMap ways tagged S61. Lots follow the GDDKiA contract sections and are all open: from the Augustów bypass in 2014 to the Łomża bypass in 2024 (full standard in 2025). Each lot is its own contract with its own opening date. The one-carriageway Stawiski bypass (2013) and the DK63 and DK64 spurs built in the Łomża contracts are not split out or drawn. Contract values come from GDDKiA pages and pl.wikipedia, and each says where the VAT basis is not stated.

Total length
215 km
Open today
215 km
Sections
13
Cost on record
€1.4B
8 of 13 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of S61 expressway Via Baltica (Ostrów Mazowiecka – Łomża – Ełk – Suwałki – Budzisko): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Podborze – Śniadowo (from the S8)

Starts at the Podborze junction with the S8 and includes the Komorowo junction; the works also rebuilt about 3 km of the existing S8. Best offer chosen on 21 November 2019. GDDKiA gave the value of the 2020 contract as nearly 750 mln zł, which is not an exact figure and is not recorded as a cost. pl.wikipedia dates the permanent traffic organisation to 13 August 2024. The drawn centreline is 3% longer than the sourced 19.46 km.

Opened19 km
  1. Jan 8, 2020Tender awarded
  2. Oct 13, 2023Opened
––
  • PolaquaBuilder
–
Śniadowo – Łomża Południe

Includes the Śniadowo junction. No contract value is given on the MSBD page. pl.wikipedia gives 11 October 2018 as the signing date, but the MSBD page dates the contract to 9 February 2018 and gives 11 October 2018 for the terminated Łomża Zachód – Kolno contract, so the MSBD date is used. The drawn centreline is 4% shorter than the sourced length.

Opened17 km
  1. Feb 9, 2018Tender awarded
  2. Jul 14, 2021Opened
––
  • PolaquaBuilder
–
Łomża Południe – Łomża Zachód (Łomża bypass, southern part)

Includes the Łomża Południe junction, where the 8.9 km DK63 spur to Zambrów starts; the spur is not drawn and not counted in the length. The contract value is stated as more than 218.1 mln zł. pl.wikipedia gives 22 December 2017 for the signing (the GDDKiA release and MSBD give 21 December) and dates the opening to 2 June 2023, after the Łomża Zachód junction was finished; the MSBD date of the main carriageways is used. The drawn centreline is 7% shorter than the sourced length.

Opened7 km
  1. Dec 21, 2017Tender awarded
  2. Mar 15, 2022Opened
––
  • Mota-Engil Central EuropeBuilder
Contract value zł218.1M
Łomża Zachód – Kolno (Łomża bypass, northern part, with the Narew bridge)

Includes the Nowogród and Łomża Północ junctions and the 1.2 km bridge over the Narew valley (1,205 m per pl.wikipedia). The 6.96 km DK64 Łomża Północ – Elżbiecin road built in the same contract is not drawn and not counted. The offer chosen on 23 March 2022 was 713.4 mln zł (pl.wikipedia); the contract value is not stated separately, so no cost is recorded. The sourced S61 length is 12.92 km (MSBD); pl.wikipedia gives 12.99 km. The drawn centreline is 1% longer than the sourced length.

Opened13 km
  1. May 19, 2022Tender awarded
  2. Sep 30, 2024Opened
––
  • IntercorBuilder
–
Kolno – Stawiski

Includes the Kolno junction, where DK63 joins; the 2.25 km DK63 stretch is not drawn and not counted. The contract also covered the second carriageway of part of the Stawiski bypass, whose first carriageway opened on 19 December 2013; that part is not split out. The contract value is the construction contract value quoted by GDDKiA on 31 October 2017. The drawn centreline is 5% shorter than the sourced length.

Opened16 km
  1. Oct 31, 2017Tender awarded
  2. Aug 9, 2021Opened
––
  • StrabagBuilder
Contract value zł288.3M
Stawiski – Szczuczyn (to the Szczuczyn bypass)

Starts after the Stawiski junction, includes the Grabowo junction and ends where the Szczuczyn bypass begins. The contract also covered the second carriageway of part of the Stawiski bypass (first carriageway opened on 19 December 2013), which is not split out. The end of the lot is not at a mapped node: the boundary is placed by the sourced length, about 3.9 km before the OSM Szczuczyn junction. The drawn centreline is 1% shorter than the sourced 18 km.

Opened18 km
  1. Oct 31, 2017Tender awarded
  2. Jul 20, 2021Opened
––
  • BudimexBuilder
Contract value zł342.1M
Szczuczyn bypass

Includes the Szczuczyn junction. Built as one carriageway with reserve for the second. The second carriageway (6.59 km, Polaqua, contract of 26 May 2017, lowest offer 75.08 mln zł) opened on 15 May 2020 under CEF funding. Length 8 km per pl.wikipedia. The ends are not at mapped nodes: the boundaries are placed by the sourced length, about 3.9 km before and 3.6 km after the OSM Szczuczyn junction. The second carriageway was added over 2.897 km from the Łomża side and 3.691 km from the Grajewo side (MSBD). The drawn centreline is 6% shorter than the sourced length.

Opened8 km
  1. Aug 11, 2014Tender awarded
  2. Nov 13, 2015Opened
––
  • PolaquaBuilder
  • FCC ConstrucciónBuilder
–
Szczuczyn – Ełk Południe

Includes the Ełk Południe junction. Works began in March 2020 and the contract deadline was 31 July 2022 (MSBD). The start is the end of the Szczuczyn bypass, not a mapped node; that boundary is placed by the sourced length. Co-financed by the Connecting Europe Facility. The drawn centreline is 12% shorter than the sourced length.

Opened23 km
  1. Aug 6, 2018Tender awarded
  2. Mar 2020Construction start
  3. Sep 13, 2022Opened
––
  • PorrBuilder
  • UnibepBuilder
Contract value zł699.51M
Ełk Południe – Wysokie (with the link to the S16 Ełk bypass)

The sourced 22.95 km is the MSBD length of the S61/S16 section, which includes about 3.4 km of connection to the S16 Ełk bypass; the drawn line follows the S61 only and ends at the Kalinowo junction, which OSM records with the old name Wysokie (ref 15) and which MSBD counts in the next lot. pl.wikipedia gives a contract value of 685,948,284.67 zł; the MSBD figure is recorded. Co-financed by the Connecting Europe Facility. The drawn centreline is 5% shorter than the sourced length.

Opened23 km
  1. Jul 19, 2018Tender awarded
  2. Aug 12, 2023Opened
––
  • TrakcjaBuilder
  • Mostostal WarszawaBuilder
  • Przedsiębiorstwo Eksploatacji Ulic i MostówBuilder
Contract value zł686.86M
Wysokie – Raczki

Ends at the Raczki junction, where the S61 meets DK8. Co-financed by the Connecting Europe Facility. The Wysokie end is taken at the Kalinowo junction (OSM old name Wysokie), which MSBD lists in this lot. The drawn centreline is 10% shorter than the sourced length.

Opened20 km
  1. Jul 4, 2018Tender awarded
  2. Dec 30, 2021Opened
––
  • BudimexBuilder
Contract value zł484.29M
Raczki – Suwałki Południe (Augustów bypass, S61 part)

The two-carriageway S61 part of the Augustów bypass, from the Raczki junction to the Suwałki Południe junction. The 659 mln zł contract (gross) covers the whole 34.23 km bypass, including 21.48 km of single-carriageway DK8 and a 2.4 km county road link, so it is not the cost of this lot alone and is not recorded as such. Co-financed under the Infrastructure and Environment programme (POIiŚ). The drawn centreline is 6% shorter than the sourced length.

Opened13 km
  1. Mar 11, 2011Tender awarded
  2. Nov 6, 2014Opened
––
  • BudimexBuilder
–
Suwałki bypass (Suwałki Południe – Suwałki Północ)

Runs from the Suwałki Południe junction past the new Suwałki Zachód junction to the Suwałki Północ junction (not included). Cement concrete surface, a first on the S61 in Podlasie. Contract value 299.4 mln zł for 34 months excluding winters (GDDKiA, 2015). Co-financed by the Connecting Europe Facility. The drawn centreline is 5% shorter than the sourced length.

Opened13 km
  1. Sep 29, 2015Tender awarded
  2. Apr 13, 2019Opened
––
  • BudimexBuilder
Contract value zł299.4M
Suwałki Północ – Budzisko (Lithuanian border)

Includes the Suwałki Północ and Szypliszki junctions, the Budzisko rest areas and ends at the Lithuanian border, where the road continues as the A5 towards Kaunas. Contract of 8 January 2020 with Budimex at 1.037 bn zł (pl.wikipedia; GDDKiA: more than 1 bn zł); contract deadline 7 April 2023. Co-financed by the Connecting Europe Facility. The drawn centreline is 4% shorter than the sourced length.

Opened24 km
  1. Jan 8, 2020Tender awarded
  2. Dec 22, 2022Opened
––
  • BudimexBuilder
Contract value zł1B

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Related projects

Sources

  1. Wikipedia (pl): Droga ekspresowa S61 (Polska)read Oct 10, 2026
  2. GDDKiA MSBD: Podborze - Śniadoworead Oct 10, 2026
  3. GDDKiA MSBD: S61 Śniadowo - Łomża Południeread Oct 10, 2026
  4. GDDKiA MSBD: Łomża Południe - Łomża Zachódread Oct 10, 2026
  5. GDDKiA MSBD: Łomża Zachód - Kolno wraz z budową odcinka drogi krajowej nr 64 Łomża Północ - Elżbiecinread Oct 10, 2026
  6. GDDKiA MSBD: Kolno - Stawiskiread Oct 10, 2026
  7. GDDKiA MSBD: S61 Stawiski - do obwodnicy Szczuczynaread Oct 10, 2026
  8. GDDKiA MSBD: S61 obwodnica Szczuczyna, II jezdniaread Oct 10, 2026
  9. GDDKiA MSBD: S61 Szczuczyn - Ełk Południe (z węzłem)read Oct 10, 2026
  10. GDDKiA MSBD: S61/S16 Ełk Południe (bez węzła) - Wysokie (bez węzła)read Oct 10, 2026
  11. GDDKiA MSBD: S61 Wysokie - węzeł Raczkiread Oct 10, 2026
  12. GDDKiA MSBD: S61/DK8 obwodnica Augustowaread Oct 10, 2026
  13. GDDKiA MSBD: S61 obwodnica Suwałkread Oct 10, 2026
  14. GDDKiA MSBD: S61 koniec obw. Suwałk – Budzisko z obw. Szypliszek - kontynuacjaread Oct 10, 2026
  15. GDDKiA: Realizacja trasy Via Baltica staje się faktem (27 April 2017)read Oct 10, 2026
  16. GDDKiA: Powstaną kolejne odcinki S61 w ramach trasy Via Baltica (31 October 2017)read Oct 10, 2026
  17. GDDKiA: Obwodnica Łomży w realizacji (21 December 2017)read Oct 10, 2026
  18. GDDKiA: Via Baltica – nowe umowy, nowi wykonawcy (8 January 2020)read Oct 10, 2026
  19. GDDKiA: Obwodnica Suwałk - umowa podpisana (29 September 2015)read Oct 10, 2026
  20. GDDKiA: Obwodnica Augustowa dostępna dla kierowców (7 November 2014)read Oct 10, 2026
  21. OpenStreetMap: ways tagged ref=S61 (Overpass query, data of 2026-10-10)read Oct 10, 2026
  22. OpenStreetMap contributors (ODbL)read Oct 10, 2026

Figures last checked against their sources in Oct 10, 2026.