Oar – Satu Mare Expressway (Someș Expres)
Expressway of 10.83 km between the Satu Mare ring road and the Hungarian border at Oar, where it meets the Hungarian M49. CNAIR signed the execution contract with Construcții Erbașu on 21 October 2025: 720.48 million lei excluding VAT, 24 months. The profile is 2×2 lanes with two junctions, two parking areas and a maintenance centre.
- Total length
- 11 km
- Open today
- 0 km
- Sections
- 1
- Cost on record
- €142.884M
- 1 of 1 sections carry a comparable figure
Restated into EUR at 2025 prices.
Sections
| Sections | Status | Length | Timeline | Cost | Funding | Contractors | Contract terms |
|---|---|---|---|---|---|---|---|
| Oar (Hungarian border) – Satu Mare Execution contract (FIDIC Red) signed on 21 October 2025, 24 months. No works start order is sourced. OpenStreetMap maps the carriageways as under construction with Construcții Erbașu as builder; that is a mapper's tag, not a start date. The drawn line runs from the M49 end at the border to the DN19 end of the mapped works (about 11.9 km, 10% above the recorded length). | Tendered | 11 km |
| – |
|
| 24 mo execution · 24 mo total · Contract value lei 720.48M |
Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.
Funding
- European Union11 km1 section
- Transport Programme 2021–2027
A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.
Related projects
- HighwaysA3 Transylvania Motorway (Brașov–Cluj–Borș)Same contractor: Construcții Erbașu
- RailwaysBucharest Metro Line M2 (Pipera – Tudor Arghezi)Same contractor: Construcții Erbașu
- HighwaysA0 Bucharest Ring MotorwaySame country and category
- HighwaysA1 Bucharest–Nădlac MotorwaySame country and category
- HighwaysA10 motorway (Sebeș–Turda)Same country and category
- HighwaysA11 Arad–Oradea MotorwaySame country and category