Railways

Bucharest – Constanța railway (CFR Line 800) upgrade

Upgrade of CFR's main line between Bucharest and the Black Sea port of Constanța, via Ciulnița, Fetești and Medgidia. Since July 2014 passenger trains run at up to 160 km/h and freight trains at up to 120 km/h on most of the route; the fastest trains cover the 225 km between Bucharest and Constanța in under two hours.

Total length
225 km
Open today
225 km
Sections
1
Loading map data…

Sections

Sections of Bucharest – Constanța railway (CFR Line 800) upgrade: status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Bucharest – Constanța

Line 800 upgrade to 160 km/h for passenger and 120 km/h for freight traffic, completed by July 2014. CFR states the investment value in two parts: 451 million EUR for București Băneasa – Fetești (works 2005–2012, ISPA and state budget) and 433 million EUR for București Nord – București Băneasa and Fetești – Constanța (works 2006–2012, JBIC loan, DEXIA Kommunalkredit credit and state budget). CFR does not say whether VAT is included or whether these are final costs. Club Feroviar (2024) gives 356.3 million EUR of financing for București Nord – Băneasa and Fetești – Constanța. JICA's ex-post evaluation (2013) puts the actual cost of the JBIC-financed sections (București Nord – Băneasa and Fetești – Constanța, 82 km) at 78,862 million JPY, including 11,883 million JPY of tax, or 536 million EUR at an average 147 JPY/EUR, against 342 million EUR planned at appraisal in 2000. Bidding for the civil works on those sections ran from May 2004 to November 2005 and the works from December 2005 to October 2010. CFR's ISPA project sheet (measure ISPA/2000/RO/16/P/PT/001) gives a total project value of 388,900,970.41 EUR for București Băneasa – Fetești (141 km), delivered through 15 works contracts and 2 technical assistance and supervision contracts (DE Consult). In 2016 the European Commission approved 226.6 million EUR from the Cohesion Fund (Transport Operational Programme 2007–2013) to refinance retrospectively the București Nord – Băneasa and Fetești – Constanța sections, a project valued at almost 475 million EUR and first financed by the Romanian state.

Opened225 km
  1. 2005Construction start
  2. Jul 2014Opened
–
  • European UnionEU co-financed upgrade of the Bucharest–Constanța line (TEN-T Rhine–Danube Corridor)
  • National budget
  • LoanJBIC (Japan Bank for International Cooperation) loan for București Nord – Băneasa and Fetești – Constanța
  • LoanDEXIA Kommunalkredit Bank AG credit for București Nord – Băneasa and Fetești – Constanța
  • European UnionCohesion Fund, Transport Operational Programme 2007–2013: retrospective refinancing of București Nord – Băneasa and Fetești – Constanța, approved in 2016
  • Astaldi (Fundulea – Fetești)Builder
  • Swietelsky (Cernavodă – Constanța, with Wiebe)Builder
  • Wiebe (Cernavodă – Constanța, with Swietelsky)Builder
  • TERNA (București Băneasa – Fundulea track)Builder
  • Klearchos G. Routsis – K. Kourtidis (stations, Fundulea – Fetești)Builder
  • IMSAT (signalling, București Băneasa – Fetești; stations, București Băneasa – Fundulea)Builder
  • Siemens (signalling and catenary, București Băneasa – Fetești)Builder
  • Colas Rail (catenary, București Băneasa – Fundulea)Builder
  • SPL Powerlines (catenary, Fundulea – Fetești)Builder
–

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union450 km
    2 sections
    • EU co-financed upgrade of the Bucharest–Constanța line (TEN-T Rhine–Danube Corridor)
    • Cohesion Fund, Transport Operational Programme 2007–2013: retrospective refinancing of București Nord – Băneasa and Fetești – Constanța, approved in 2016
  • Loan450 km
    2 sections
    • JBIC (Japan Bank for International Cooperation) loan for București Nord – Băneasa and Fetești – Constanța
    • DEXIA Kommunalkredit Bank AG credit for București Nord – Băneasa and Fetești – Constanța
  • National budget225 km
    1 section

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. Wikipedia: Căile Ferate Române Line 800
  2. Capital: Premieră absolută în România: Un tren circulă cu 160 km/h pe oră!
  3. Club Feroviar: EXCLUSIV. S-au modernizat mai mulți km de cale ferată cu fonduri preaderare decât postaderare (2024-10-31)read Sep 25, 2026 · archived copy
  4. Club Feroviar: FOTO. 10 ani de 160 km/oră pe București-Constanța. Locomotiva inaugurală, pe butuci (2024-07-04)read Sep 25, 2026
  5. JICA: Romania, Ex-Post Evaluation of Japanese ODA Loan Project, Railway Rehabilitation Project of Bucharest-Constanta Line (2013)read Sep 28, 2026
  6. CFR: Măsura ISPA/2000/RO/16/P/PT/001 Reabilitarea liniei de cale ferată București – Constanța, secțiunile București Băneasa – Fundulea, Fundulea – Lehliu, Lehliu – Ciulnița – Feteștiread Oct 1, 2026
  7. HotNews: Comisia Europeana a aprobat 226 de milioane de euro, finantare retroactiva pentru reabilitarea a doua tronsoane din calea ferata Bucuresti – Constanta (2016-10-17)read Oct 1, 2026