București – Jilava – Giurgiu Nord – Giurgiu Nord Frontieră railway modernisation

Design-and-build modernisation of CFR lines 103 and 106A between București Progresu, Jilava, Giurgiu Nord and Giurgiu Nord Frontieră, the approach to the Giurgiu–Ruse bridge. Lot 2 covers electrification, signalling and ERTMS Level 2. Works are under way, with traffic suspended between Jilava and Frătești from 16 March 2026.

Total length
64 km
Open today
0 km
Under construction
64 km
Sections
1
Cost on record
€418.106M
1 of 1 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of București – Jilava – Giurgiu Nord – Giurgiu Nord Frontieră railway modernisation: status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Lot 2: București Progresu – Jilava – Giurgiu Nord – Giurgiu Nord Frontieră

Contract signed on 14 August 2025 with the RailWorks association (Arcada Company as leader, Alstom Transport): 6 months of design, 30 months of works, 120 months of guarantee and 2 months of post-acceptance activities, 158 months in total. CFR states that traffic is suspended between Jilava and Frătești from 16 March 2026 for the works, with similar measures to follow on București Progresu – Jilava and Frătești – Giurgiu Nord Frontieră; CFR estimates completion and reopening for September 2028. CFR's release of 12 March 2026 says the conditions for starting works are met and gives no start date for works, so the start is recorded as March 2026 only. Length measured from OpenStreetMap geometry (one track, from București Progresu to the start of the Giurgiu–Ruse bridge approach). The Giurgiu–Ruse bridge is a separate project and is not included in this length.

Under construction
7 of 30 contracted months
64 km
  1. Aug 14, 2025Tender awarded
  2. Mar 2026Construction start
  3. Sep 2028Expected opening
–
  • European UnionConnecting Europe Facility 2021–2027, grant agreement no. 101122601 (22-RO-TC-Giurgiu Stage II), with state budget co-financing
  • National budget
  • RailWorks (Arcada Company – Alstom Transport)Builder
6 mo design · 30 mo execution · 158 mo total · 120 mo guarantee · Contract value lei 2.1B

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union64 km
    1 section
    • Connecting Europe Facility 2021–2027, grant agreement no. 101122601 (22-RO-TC-Giurgiu Stage II), with state budget co-financing
  • National budget64 km
    1 section

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Sources

  1. CFR SA: 14 August 2025, semnarea contractului pentru modernizarea liniei București Nord – Jilava – Giurgiu Nord – Giurgiu Nord Frontieră, Lot 2read Oct 5, 2026
  2. CFR SA: comunicat din 12 martie 2026, începerea lucrărilor de modernizare București Progresu – Jilava – Giurgiu Nord Frontierăread Oct 5, 2026
  3. OpenStreetMap contributors (geometry of CFR lines 103 and 106A, ODbL)read Oct 5, 2026