Corridor X Railway Modernisation (Belgrade – Niš)

Upgrade of Serbian mainline 102 between Belgrade and Niš to 200 km/h, backed by an EIB, EBRD and EU financing package reported at up to EUR 2.2 billion for the corridor as a whole. Stalać–Đunis, where a new double-track alignment is to be built, was contracted on 27 November 2025, with works announced to start in March 2027. A prequalification call for one contract covering Paraćin–Stalać, Đunis–Trupale and Trupale–Međurovo opened on 4 August 2026. No construction start or opening date is recorded for any subsection. Published subsection lengths disagree with each other: 83, 62 and 58 km for the three northern subsections against 48.3 km given for Paraćin–Trupale–Međurovo. Lengths here are therefore measured off the mapped existing alignment, cut at the stations that bound each subsection, and the geometry follows the line in use today rather than the new Stalać–Đunis alignment. The EUR 2.2 billion figure covers the whole programme and is not apportioned per subsection; the only per-lot figure recorded is the Stalać–Đunis contract value.

Total length
236 km
Open today
0 km
Sections
6
Cost on record
€348.905M
1 of 6 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of Corridor X Railway Modernisation (Belgrade – Niš): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Belgrade Centre – Velika PlanaPlanned88 km––
  • LoanEuropean Investment Bank and EBRD.
  • European UnionEU grant support via WBIF.
  • National budget
––
Velika Plana – Paraćin

Feasibility study, preliminary design and ESIA by a SAFEGE (SUEZ Consulting) consortium with Egis, EPEM and KPMG under the EU PPF9 facility. The study covers the 50 km Velika Plana – Gilje part of the lot. No builder has been chosen.

Planned62 km––
  • LoanEuropean Investment Bank and EBRD.
  • European UnionEU grant support via WBIF.
  • National budget
  • SUEZ Consulting (SAFEGE) – Egis – EPEM – KPMG consortium (PPF9)Designer
–
Paraćin – Stalać

Feasibility study, preliminary design and ESIA by a SAFEGE (SUEZ Consulting) consortium with Egis, EPEM and KPMG under the EU PPF9 facility, for Paraćin – Trupale (61 km, excluding Stalać – Đunis). They are not the builder.

Tendered21 km––
  • LoanEuropean Investment Bank and EBRD.
  • European UnionEU grant support via WBIF.
  • National budget
  • SUEZ Consulting (SAFEGE) – Egis – EPEM – KPMG consortium (PPF9)Designer
–
Stalać – Đunis

Works announced to start in March 2027 (President Vučić, reported by Infrastruktura železnice Srbije on 21 June 2026). The design-and-build contract excludes Tunnel No. 4 (3,275 m), procured separately; that 2021 tender (TED 384541-2021) was discontinued. Design speed 160 km/h for this subsection per the 2022 contract notice.

Tendered19 km
  1. Nov 27, 2025Tender awarded
  2. ≈2031Expected openingProjected from contract
–
  • LoanEuropean Investment Bank and EBRD.
  • European UnionEU grant support via WBIF.
  • National budget
  • GULERMAK AGIR SANAYI İNSAAT VE TAAHHUT A.S. & YSE Yapı Sanayi ve Ticaret A.S.Builder
68 mo total · Contract value €348.905M
Đunis – Trupale (Niš)

Feasibility study, preliminary design and ESIA by a SAFEGE (SUEZ Consulting) consortium with Egis, EPEM and KPMG under the EU PPF9 facility, for Paraćin – Trupale (61 km, excluding Stalać – Đunis). They are not the builder.

Tendered40 km––
  • LoanEuropean Investment Bank and EBRD.
  • European UnionEU grant support via WBIF.
  • National budget
  • SUEZ Consulting (SAFEGE) – Egis – EPEM – KPMG consortium (PPF9)Designer
–
Trupale – Međurovo (Niš)

Reconstruction of the existing line, with new passenger platforms and an underpass at Niš Ranžirna station. 6.7 km per the August 2026 contract notice, the third subsection of the 65.2 km tender with Paraćin – Stalać and Đunis – Trupale. The line runs via Niš Ranžirna and bypasses Niš station; the mapped geometry measures 6.83 km.

Tendered7 km––
  • LoanEuropean Investment Bank and EBRD.
  • European UnionEU grant support via WBIF.
  • National budget
––

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • Loan236 km
    6 sections
    • European Investment Bank and EBRD.
  • European Union236 km
    6 sections
    • EU grant support via WBIF.
  • National budget236 km
    6 sections

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Corridors

The designations this project is recorded under. Both schemes are kept: the Pan-European corridors are how these projects were described when they were planned, and TEN-T is what EU money is allocated on today.

  • Pan-European Corridor XPan-European

Sources

  1. EBRD: Corridor X rail Belgrade–Niš project summary (subsection lengths)
  2. European Investment Bank: Serbia Corridor X railway
  3. EU za tebe: Koridor X: železnička pruga Beograd–Niš, deonica Paraćin–Trupale–Međurovo
  4. OpenStreetMap: relation 1335434, Магистрална пруга 102
  5. OpenStreetMap contributors: route geometry (ODbL)
  6. TED: Contract award notice 846958-2025, Belgrade – Niš, section Stalać – Đunis, Lot 2 (19 December 2025)read Sep 25, 2026
  7. TED: Contract notice 323154-2022, design and works for the Belgrade – Niš section Stalać – Đunis (2022)read Sep 25, 2026
  8. Infrastruktura železnice Srbije: Predsednik Vučić obišao novoizgrađeni Jedinstveni dispečerski centar (21 June 2026)read Sep 25, 2026
  9. TED: Contract notice 538901-2026, Section 3 Paraćin – Trupale – Međurovo (design and build), Belgrade – Niš Railway Modernisation Project (4 August 2026)read Sep 25, 2026
  10. Pruga Beograd–Niš, deonica II Velika Plana–Paraćin: Netehnički rezime (PPF9)read Sep 28, 2026
  11. Pruga Beograd–Niš, deonica III Paraćin–Trupale: Netehnički rezime (PPF9)read Sep 28, 2026
  12. TV Zona Plus: Raspisan međunarodni tender za izvođača radova na deonici pruge između Beograda i Niša (4 August 2026)read Oct 2, 2026