R4 expressway (Košice – Prešov – Svidník – Polish border)
North–south expressway planned from the Hungarian border at Milhosť through Košice, Prešov and Svidník to the Polish border at Vyšný Komárnik (sk.wikipedia: 144 km with the stretches shared with the D1 and R2). Four parts are modelled here: Košice – Milhosť (opened 2013), the half-profile Svidník bypass (opened 2010), the first stage of the Prešov north bypass with the Bikoš tunnel (opened 2023) and the second stage with the Okruhliak tunnel (under construction). The shared stretches with the D1 and the R2 are counted in those projects. The sections between Kapušany and the Polish border are in preparation and are not drawn.
- Total length
- 33 km
- Open today
- 23 km
- Under construction
- 10 km
- Sections
- 4
- Cost on record
- €353.37M
- 1 of 4 sections carry a comparable figure
Restated into EUR at 2025 prices.
Sections
| Sections | Status | Length | Timeline | Cost | Funding | Contractors | Contract terms |
|---|---|---|---|---|---|---|---|
| Košice, Juh – Milhosť (Hungarian border) Full profile from the start, category R 24,5/120 (R 24,5/100 between Kechnec and the border). 16 bridges and 2 interchanges, among them the 530 m bridge over the broad-gauge railway. sk.wikipedia gives construction costs of EUR 78 million against an initial state expert estimate of EUR 117 million; the VAT basis and price year are not stated, so neither is recorded as a money field. The drawn line starts at the Košice, Juh interchange and ends at the border (14.1 km, about 1% under the recorded length). The section east of Košice, Juh up to Košické Oľšany shares the route of the R2 and is not part of this lot. | Opened | 14 km |
| – | – |
| – |
| Svidník bypass (half profile) Built as a single carriageway (half profile, category R 11,5/100 or R 22,5/100) with 9 bridges, the Svidník, Juh interchange and an at-grade connection at Svidník, Sever. The left half is not scheduled before 2028 per sk.wikipedia. The drawn line is 4.4 km, about 4% under the recorded length. | Opened | 5 km |
| – | – |
| – |
| Prešov north bypass, I. stage (Prešov, Západ – Prešov, Sever, Bikoš tunnel) Full profile, category R 24,5/100, with the twin-tube Bikoš tunnel (1,155 m), 9 bridges (3 on the R4, 3 on the interchange ramps, 3 off the route) and a rebuilt I/68 at the Prešov, Sever interchange. The Prešov, Západ interchange joins the D1. Contract duration converted from days: 1340 days. The drawn line is 4.0 km, 7% under the recorded length. | Opened | 4 km |
| – |
|
| 44 mo execution · Contract value €142.877M |
| Prešov north bypass, II. stage (Prešov, Sever – Kapušany, Okruhliak tunnel) Full profile, 10.2 km from the Prešov, Sever interchange to the Kapušany interchange on I/18, with the twin-tube Okruhliak tunnel (1,800 m, NDS), 12 bridges and 6 noise barriers (3,683 m in total). Contractor is the Združenie R4 severný obchvat Prešova II. etapa: the NDS page lists Marti as the fifth member, while the 2023 press report named TuCon. Contract duration converted from days: 1464 days. The contract deadline is the last quarter of 2027, not recorded as an expected opening; Korzár (5 April 2026, via sk.wikipedia) reports that NDS expects to open in summer 2028. The drawn line (10.0 km) starts at the first mapped construction way, about 1 km beyond the Prešov, Sever interchange where the I. stage ends. | Under construction 37 of 48 contracted months | 10 km |
|
|
|
| 48 mo execution · Contract value €338M |
Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.
Funding
- European Union15 km2 sections
- NDS press release of 24 August 2021: more than EUR 57.6 million from the European Regional Development Fund (headline: almost EUR 60 million), a non-repayable contribution. The operational programme is not named.
- Connecting Europe Facility (CEF), military mobility call: more than EUR 69 million, shared between this stage and the design of the R4 sections between Kapušany and the Polish border.
- National budget15 km2 sections
- NDS: the construction is financed from the state budget.
- NDS project page: state budget and CEF.
A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.
Related projects
- HighwaysD3 motorway (Hričovské Podhradie – Žilina – Čadca – Polish border)Same contractor: Eurovia, SMS, Skanska, Strabag, Váhostav
- HighwaysD35 motorway (Sedlice – Olomouc – Lipník nad Bečvou)Same contractor: Eurovia, Skanska, Strabag, TuCon
- HighwaysR2 expressway (Trenčín – Prievidza – Zvolen – Lučenec – Rimavská Sobota – Rožňava – Košice)Same contractor: Eurovia, Inžinierske stavby, Strabag, Váhostav
- HighwaysR3 expressway (Orava and Turiec sections)Same contractor: Inžinierske stavby, Skanska, Strabag, Váhostav
- HighwaysD0 Prague Ring Road (Pražský okruh)Same contractor: Eurovia, Skanska, Strabag
- HighwaysD1 motorway (Praha – Brno – Ostrava – Polish border)Same contractor: Inžinierske stavby, Skanska, Strabag
Sources
- Wikipedia (sk): Rýchlostná cesta R4 (Slovensko), section table and 'Úseky' proseread Oct 10, 2026
- NDS: R4 Prešov – severný obchvat, II. etapa (length 10 200 m, financing, contractor association)read Oct 10, 2026
- NDS press: Začíname obstarávať II. etapu severného obchvatu R4 (notice sent 24.02.2022, expected value EUR 263 million)read Oct 10, 2026
- Aktuality.sk, 29.6.2023: Obchvat Prešova môže pokračovať, diaľničiari podpísali zmluvu s víťazom tendraread Oct 10, 2026
- NDS press: Tunel Okruhliak má už vyrazený skoro kilometer (II. etapa figures, CEF grant above EUR 69 million)read Oct 10, 2026
- NDS press: Severný obchvat Prešova sa začne stavať koncom júla (I. etapa 4,3 km, Bikoš tunnel 1 155 m, 1 340 days)read Oct 10, 2026
- NDS press: Tunel Prešov je prerazený o tri mesiace skôr (I. etapa winner Váhostav – SK and TuCon, EUR 142 876 816 excluding VAT)read Oct 10, 2026
- NDS press: Tunel Bikoš je prerazený. Najťažšie práce sú za nami (I. etapa under construction since July 2019)read Oct 10, 2026
- NDS press: Na výstavbu I. etapy prešovskej R4 sme získali takmer 60 miliónov z fondov EÚread Oct 10, 2026
- OpenStreetMap: ways with ref=R4 (highway=motorway, trunk and construction), Overpass query of 2026-10-10read Oct 10, 2026
- OpenStreetMap contributors: route geometry (ODbL)read Oct 10, 2026