CFR Line 300 rehabilitation, Rhine–Danube Corridor (Câmpina–Predeal and Coșlariu–Sighișoara)
Rehabilitation of two sections of CFR Line 300, part of the TEN-T Rhine–Danube Corridor, for speeds of up to 160 km/h. The 48 km Câmpina–Predeal mountain section was upgraded in 2007–2011 with ISPA co-funding, cutting Bucharest–Brașov journey times to 2 h 40 min. The nearly 100 km Coșlariu–Sighișoara section was rebuilt in 2012–2018 on a new alignment with new bridges and tunnels, among them the 969 m Daneș Tunnel, the longest railway tunnel built in Romania after 1989.
- Total length
- 148 km
- Open today
- 148 km
- Sections
- 2
- Cost on record
- €1.2B
- 2 of 2 sections carry a comparable figure
Restated into EUR at 2025 prices.
Sections
| Sections | Status | Length | Timeline | Cost | Funding | Contractors | Contract terms |
|---|---|---|---|---|---|---|---|
| Câmpina – Predeal Line 300 rehabilitation on the TEN-T Rhine–Danube Corridor: Câmpina–Predeal 2007–2011 (ISPA, 75% EU / 25% government), Coșlariu–Sighișoara 2012–2018 to 160 km/h incl. the 969 m Daneș tunnel. Câmpina – Predeal ran as six works contracts: Lot 1 track and earthworks (Porr Bau, awarded 24 May 2007), Lots 2.1–2.3 culverts and bridges (2008), Lot 3 catenary (awarded 2007 to Spie Rail, later Colas Rail, with ISAF) and Lot 4 signalling (Ansaldo STS with ISAF); ISPCF designed all lots. The tender award date is the Lot 1 contract. | Opened | 48 km |
|
|
|
| – |
| Coșlariu – Sighișoara Line 300 rehabilitation on the TEN-T Rhine–Danube Corridor: Câmpina–Predeal 2007–2011 (ISPA, 75% EU / 25% government), Coșlariu–Sighișoara 2012–2018 to 160 km/h incl. the 969 m Daneș tunnel | Opened | 100 km |
|
|
|
| Contract value lei 2.3B |
Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.
Funding
- European Union148 km2 sections
- About €200M co-funded through the ISPA programme (75% EU, 25% Romanian government).
- TEN-T Rhine–Danube Corridor upgrade, EU co-financed
- National budget148 km2 sections
A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.
Related projects
- HighwaysA1 Bucharest–Nădlac MotorwaySame contractor: Alpine Bau, FCC Construcción, Porr
- TunnelsRomanian railway tunnelsSame contractor: Arcada Company, FCC Construcción, Porr
- HighwaysS61 expressway Via Baltica (Ostrów Mazowiecka – Łomża – Ełk – Suwałki – Budzisko)Same contractor: FCC Construcción, Porr
- HighwaysS7 expressway (Gdańsk – Elbląg – Warszawa – Radom – Kielce – Kraków – Rabka)Same contractor: Bilfinger Berger, Porr
- HighwaysS8 expressway (Wrocław – Łódź – Warszawa – Białystok)Same contractor: Bilfinger Berger, Porr
- HighwaysA11 Arad–Oradea MotorwaySame contractor: FCC Construcción, Porr
Corridors
The designations this project is recorded under. Both schemes are kept: the Pan-European corridors are how these projects were described when they were planned, and TEN-T is what EU money is allocated on today.
- TEN-T Rhine–Danube CorridorTEN-T
Sources
- Wikipedia: Căile Ferate Române Line 300
- Railway PRO: Romania to complete a new Corridor IV rail section this year
- Adevărul: Lucrare publică din România, premiată de UE
- hotnews.ro
- eur-lex.europa.eu
- CFR: Măsura ISPA 2003/RO/P/PT/007 – Reabilitarea liniei de cale ferată București – Brașov, secțiunea Câmpina – Predealread Sep 28, 2026
- CFR: Arhivă comunicate ISPA 2011read Sep 28, 2026
- CFR: Arhivă comunicate de presă ISPAread Sep 28, 2026