CFR Line 300 rehabilitation, Rhine–Danube Corridor (Câmpina–Predeal and Coșlariu–Sighișoara)

Rehabilitation of two sections of CFR Line 300, part of the TEN-T Rhine–Danube Corridor, for speeds of up to 160 km/h. The 48 km Câmpina–Predeal mountain section was upgraded in 2007–2011 with ISPA co-funding, cutting Bucharest–Brașov journey times to 2 h 40 min. The nearly 100 km Coșlariu–Sighișoara section was rebuilt in 2012–2018 on a new alignment with new bridges and tunnels, among them the 969 m Daneș Tunnel, the longest railway tunnel built in Romania after 1989.

Total length
148 km
Open today
148 km
Sections
2
Cost on record
€1.2B
2 of 2 sections carry a comparable figure

Restated into EUR at 2025 prices.

Loading map data…

Sections

Sections of CFR Line 300 rehabilitation, Rhine–Danube Corridor (Câmpina–Predeal and Coșlariu–Sighișoara): status, length, dates, cost, funding and contractors
SectionsStatusLengthTimelineCostFundingContractorsContract terms
Câmpina – Predeal

Line 300 rehabilitation on the TEN-T Rhine–Danube Corridor: Câmpina–Predeal 2007–2011 (ISPA, 75% EU / 25% government), Coșlariu–Sighișoara 2012–2018 to 160 km/h incl. the 969 m Daneș tunnel. Câmpina – Predeal ran as six works contracts: Lot 1 track and earthworks (Porr Bau, awarded 24 May 2007), Lots 2.1–2.3 culverts and bridges (2008), Lot 3 catenary (awarded 2007 to Spie Rail, later Colas Rail, with ISAF) and Lot 4 signalling (Ansaldo STS with ISAF); ISPCF designed all lots. The tender award date is the Lot 1 contract.

Opened48 km
  1. 2007Construction start
  2. May 24, 2007Tender awarded
  3. Dec 2011Opened
  • Estimated €199.5M(2003)
  • Actual €313.4M(2011)
  • European UnionAbout €200M co-funded through the ISPA programme (75% EU, 25% Romanian government).
  • National budget
  • Porr BauBuilder
  • Arcada CompanyBuilder
  • Construcții FeroviareBuilder
  • Vega '93Builder
  • Franz KasseckerBuilder
  • Bilfinger BergerBuilder
  • Colas RailBuilder
  • ISAFBuilder
  • Ansaldo STSBuilder
  • ISPCFDesigner
–
Coșlariu – Sighișoara

Line 300 rehabilitation on the TEN-T Rhine–Danube Corridor: Câmpina–Predeal 2007–2011 (ISPA, 75% EU / 25% government), Coșlariu–Sighișoara 2012–2018 to 160 km/h incl. the 969 m Daneș tunnel

Opened100 km
  1. 2012Tender awarded
  2. 2012Construction start
  3. 2018Opened
  • Estimated €187M(2012)
  • European UnionTEN-T Rhine–Danube Corridor upgrade, EU co-financed
  • National budget
  • FCC ConstrucciónBuilder
  • Alpine BauBuilder
  • AzviBuilder
Contract value lei 2.3B

Contractor roles are as recorded in the award. Only builders count toward the delivery rankings.

Funding

  • European Union148 km
    2 sections
    • About €200M co-funded through the ISPA programme (75% EU, 25% Romanian government).
    • TEN-T Rhine–Danube Corridor upgrade, EU co-financed
  • National budget148 km
    2 sections

A section that lists two sources counts its full length under each: the data records which sources paid, not what share each one carried.

Related projects

Corridors

The designations this project is recorded under. Both schemes are kept: the Pan-European corridors are how these projects were described when they were planned, and TEN-T is what EU money is allocated on today.

  • TEN-T Rhine–Danube CorridorTEN-T

Sources

  1. Wikipedia: Căile Ferate Române Line 300
  2. Railway PRO: Romania to complete a new Corridor IV rail section this year
  3. Adevărul: Lucrare publică din România, premiată de UE
  4. hotnews.ro
  5. eur-lex.europa.eu
  6. CFR: Măsura ISPA 2003/RO/P/PT/007 – Reabilitarea liniei de cale ferată București – Brașov, secțiunea Câmpina – Predealread Sep 28, 2026
  7. CFR: Arhivă comunicate ISPA 2011read Sep 28, 2026
  8. CFR: Arhivă comunicate de presă ISPAread Sep 28, 2026