Spedition UMB

Romania
Sections
30
Length
962 km
Median slip
+14 mo
Median overrun
–

Slip measured on 21 of 30 sections built.

No section this firm built records both an estimate and a final cost.

Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.

Joint ventures worked through

  • SA&PE Construct – Euro-Asfalt – Tehnostrade – Spedition UMB
  • SA&PE Construct – Spedition UMB – Tehnostrade
  • SA&PE Construct – Spedition UMB – Tehnostrade – Arcada Company
  • SA&PE Construct – Tehnostrade – Spedition UMB – Euro Asfalt
  • SA&PE Construct – Tehnostrade – Spedition UMB – Euro-Asfalt
  • Spedition UMB – Tehnostrade
  • Spedition UMB – Tehnostrade – Electromontaj
  • Spedition UMB – Tehnostrade – SA&PE Construct – Euro-Asfalt

Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.

Sections built

SectionCountryStatusLengthOpenedSlip
A0 Bucharest Ring Motorway / North half-ring: A2 – DN2RomaniaUnder construction14 km–+27 mo
A0 Bucharest Ring Motorway / North half-ring: DN2 – DN1 (via A3)RomaniaOpened19 kmDec 2024+15 mo
A1 Bucharest–Nădlac Motorway / Lugoj – Deva (lots 3–4)RomaniaOpened43 kmDec 2019–
A1 Bucharest–Nădlac Motorway / Margina – Holdea (Lugoj–Deva lot 2)RomaniaUnder construction13 km–−10 mo
A1 Bucharest–Nădlac Motorway / Timișoara – LugojRomaniaOpened35 kmDec 2015–
A3 Transylvania Motorway (Brașov–Cluj–Borș) / Zimbor – Poarta SălajuluiRomaniaOpened12 kmAug 2026+31 mo
A3 Transylvania Motorway (Brașov–Cluj–Borș) / Zimbor – Nădășelu (Mihăiești)RomaniaUnder construction30 km–+47 mo
A3 Transylvania Motorway (Brașov–Cluj–Borș) / Gilău (Cluj West) – NădășeluRomaniaOpened10 kmSep 2018–
A3 Bucharest–Brașov Motorway / Bucharest – PloieștiRomaniaOpened62 kmJul 2012+46 mo
A7 Motorway (Moldavia Motorway) / Buzău bypassRomaniaOpened5 kmJul 2025+22 mo
A7 Motorway (Moldavia Motorway) / Buzău – Râmnicu SăratRomaniaOpened31 kmNov 2024−5 mo
A7 Motorway (Moldavia Motorway) / Râmnicu Sărat – Mândrești-MunteniRomaniaOpened36 kmDec 2024−4 mo
A7 Motorway (Moldavia Motorway) / Focșani bypass (Buzău–Focșani lot 4)RomaniaOpened11 kmNov 2024+14 mo
A7 Motorway (Moldavia Motorway) / Domnești-Târg – AdjudRomaniaOpened16 kmDec 2025–
A7 Motorway (Moldavia Motorway) / Bacău bypassRomaniaOpened16 kmDec 2020−9 mo
A7 Motorway (Moldavia Motorway) / Adjud – Bacău SudRomaniaOpened46 kmAug 2026–
A7 Motorway (Moldavia Motorway) / Bacău – Roman (Bacău–Pașcani lot 1)RomaniaUnder construction30 km–+11 mo
A7 Motorway (Moldavia Motorway) / Roman – Săbăoani (Bacău–Pașcani lot 2)RomaniaUnder construction19 km–+11 mo
A7 Motorway (Moldavia Motorway) / Săbăoani – Pașcani (Bacău–Pașcani lot 3)RomaniaUnder construction28 km–+14 mo
A7 Motorway (Moldavia Motorway) / Pașcani – SuceavaRomaniaTendered62 km–+2 mo
A8 Târgu Mureș–Iași–Ungheni Motorway (Unirii) / Târgu Mureș – Ditrău (sections 1A–1D)RomaniaUnder construction92 km–+32 mo
A8 Târgu Mureș–Iași–Ungheni Motorway (Unirii) / Ditrău – Moțca (DN2) (sections 2A–2C, 3)RomaniaUnder construction119 km––
A8 Târgu Mureș–Iași–Ungheni Motorway (Unirii) / Moțca – Târgu Frumos (incl. A7 junction)RomaniaTendered27 km–−1 mo
Focșani – Brăila Expressway / Focșani (A7) – BrăilaRomaniaTendered74 km–−2 mo
Craiova–Pitești Expressway (DEx12) / Balș – SlatinaRomaniaOpened16 kmApr 2022+15 mo
Craiova–Pitești Expressway (DEx12) / Slatina bypassRomaniaOpened21 kmJul 2022+18 mo
Craiova–Pitești Expressway (DEx12) / Slatina – ColoneștiRomaniaOpened32 kmDec 2023+7 mo
Craiova–Pitești Expressway (DEx12) / Colonești – AlbotaRomaniaOpened20 kmNov 2024–
Craiova–Pitești Expressway (DEx12) / Albota – PiteștiRomaniaOpened11 kmJul 2025–
DEx6 Danube Expressway (Brăila – Galați) / Brăila – Galați (Smârdan)RomaniaUnder construction12 km––
Romanian road tunnels / Petru Vodă tunnel (A8)RomaniaUnder construction0.9 km––
Romanian road tunnels / Boureni tunnel (A8)RomaniaUnder construction0.4 km––

Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.