Tehnostrade
Romania
- Sections
- 21
- Length
- 648 km
- Median slip
- +9 mo
- Median overrun
- –
Slip measured on 16 of 21 sections built.
No section this firm built records both an estimate and a final cost.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Joint ventures worked through
- SA&PE Construct – Euro-Asfalt – Tehnostrade – Spedition UMB
- SA&PE Construct – Spedition UMB – Tehnostrade
- SA&PE Construct – Spedition UMB – Tehnostrade – Arcada Company
- SA&PE Construct – Tehnostrade – Spedition UMB – Euro Asfalt
- SA&PE Construct – Tehnostrade – Spedition UMB – Euro-Asfalt
- Spedition UMB – Tehnostrade
- Spedition UMB – Tehnostrade – Electromontaj
- Spedition UMB – Tehnostrade – SA&PE Construct – Euro-Asfalt
Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.
Sections built
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.