Trace Group Hold

BulgariaRomaniaSerbia
Sections
13
Length
262 km
Median slip
+10 mo
Median overrun
–

Slip measured on 2 of 13 sections built.

No section this firm built records both an estimate and a final cost.

Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.

Joint ventures worked through

  • DZZD Obhod Montana
  • Hemus A2 Consortium
  • Metro Druzhba consortium
  • Metro Stroitelstvo consortium
  • TRACE – MOSTOVIK

Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.

Sections built

SectionCountryStatusLengthOpenedSlip
A1 Trakia Motorway / Stara Zagora – Nova ZagoraBulgariaOpened32 kmJul 2012–
A2 Hemus Motorway / Sofia – YanaBulgariaOpened8 kmAug 2013+1 mo
Montana – Botevgrad Expressway (I-1 / E79) / Montana bypassBulgariaOpened12 kmDec 2015–
Sofia Metro Line M3 (Gorna Banya – Levski) / Stage 1: Vladimir Vazov Blvd – city centre – Zhitnitsa St (Hadzhi Dimitar – Krasno Selo)BulgariaOpened8 kmAug 2020–
Sofia Metro Line M3 (Gorna Banya – Levski) / Stage 3: Hadzhi Dimitar – Levski (Gen. Vladimir Vazov Blvd)BulgariaOpened3 kmAug 2026–
Sofia Metro Line M4 (Obelya – Sofia Airport) / Stage III, Lot 1: Tsarigradsko shose – Sofia AirportBulgariaOpened5 kmApr 2015–
A7 Motorway (Moldavia Motorway) / Mizil – Stâlpu (Ploiești–Buzău lot 2)RomaniaOpened28 kmOct 2025+18 mo
Bucharest Metro Line M4 (Gara de Nord 2 – Străulești) / Southern extension: Gara de Nord – Gara ProgresulRomaniaTendered11 km––
A1 Niš – Preševo (Corridor X south) / Grdelica – Caričina DolinaSerbiaOpened12 kmMay 2019–
A4 Niš – Dimitrovgrad (E80) / Pirot istok – DimitrovgradSerbiaOpened14 kmSep 2017–
A4 Niš – Dimitrovgrad (E80) / Dimitrovgrad bypassSerbiaOpened9 kmJun 2018–
Niš – Dimitrovgrad Railway Modernisation / Niš – DimitrovgradSerbiaUnder construction96 km––
Niš – Brestovac Railway Reconstruction / Niš – BrestovacSerbiaOpened23 kmOct 2026–

Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.