Arcada Company
Romania
- Sections
- 12
- Length
- 510 km
- Median slip
- +12 mo
- Median overrun
- +33.4%
Slip measured on 9 of 12 sections built.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Joint ventures worked through
- AKTOR – Alstom Transport – Arcada Company
- Alstom Transport – Arcada Company
- Gülermak – Alstom – Arcada JV
- RailWorks
- RailWorks (Alstom – Arcada – Euro Construct Trading '98)
- RailWorks (Arcada – Alstom)
- SA&PE Construct – Spedition UMB – Tehnostrade – Arcada Company
Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.
Sections built
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.