Arcada Company

Romania
Sections
5
Length
189 km
Median slip
+20 mo
Median overrun

Slip measured on 4 of 5 sections built.

No section this firm built records both an estimate and a final cost.

Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.

Joint ventures worked through

  • RailWorks
  • SA&PE Construct – Spedition UMB – Tehnostrade – Arcada Company

Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.

Sections built

Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.