Webuild
CzechiaGreecePolandRomaniaSlovakia
- Sections
- 18
- Length
- 559 km
- Median slip
- +57 mo
- Median overrun
- –
Slip measured on 2 of 18 sections built.
No section this firm built records both an estimate and a final cost.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Joint ventures worked through
- AEGEK – Impregilo – Ansaldo T.S.F. – SELI – AnsaldoBreda JV
- Dúha – Salini Impregilo JV
- Salini Impregilo – Secol
- Webuild – FCC Construcción – Salcef – Hitachi Rail
- Webuild – Impresa Pizzarotti – Salcef
- Webuild – Participazioni Italia – Salcef JV
- Webuild – Tancrad
Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.
Sections built
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.