Swietelsky

CzechiaCroatiaHungaryPolandRomania
Sections
14
Length
456 km
Median slip
+18 mo
Median overrun
–

Slip measured on 1 of 14 sections built.

No section this firm built records both an estimate and a final cost.

Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.

Joint ventures worked through

  • Alstom Transport – Swietelsky – Astaldi – Euro Construct Trading '98 – Dafora

Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.

Sections built

SectionCountryStatusLengthOpenedSlip
D11 motorway (Praha – Hradec Králové – Jaroměř – Trutnov – Polish border) / Hradec Králové – SmiřiceCzechiaOpened15 kmDec 2021–
D3 motorway (Praha – Tábor – České Budějovice – Dolní Dvořiště) / Bošilec – Ševětín (0309/I)CzechiaOpened8 kmJun 2019–
D3 motorway (Praha – Tábor – České Budějovice – Dolní Dvořiště) / Nažidla – border (0312/II)CzechiaOpened3 kmJul 2026–
D35 motorway (Sedlice – Olomouc – Lipník nad Bečvou) / Časy – OstrovCzechiaOpened15 kmDec 2022–
D48 motorway (Bělotín – Nový Jičín – Frýdek-Místek – Žukov) / Rybí – RychalticeCzechiaOpened13 kmDec 2020–
D6 motorway (Praha – Karlovy Vary) / Řevničov bypassCzechiaOpened4 kmNov 2020–
D6 motorway (Praha – Karlovy Vary) / Lubenec bypassCzechiaOpened5 kmAug 2021–
Praha – Benešov – Tábor – České Budějovice railway (4th transit corridor, lines 221/220) / Praha hl. n. – Praha-Hostivař (Vršovice rebuild, four tracks)CzechiaOpened7 kmJan 2021–
Zaprešić – Zabok railway modernisation and electrification (R201) / Zaprešić – ZabokCroatiaOpened24 kmSep 2022–
M44 expressway (Kecskemét – Kunszentmárton – Békéscsaba) / Kunszentmárton – CsabacsűdHungaryOpened34 kmOct 2019–
M85 expressway (Győr – Csorna – Sopron – Austrian border) / Fertőendréd (Fertőd) – NagylózsHungaryOpened16 kmDec 2020–
Railway line 8 Warszawa – Radom – Kielce – Kraków (modernisation) / Warka – Radom (second track)PolandOpened47 kmAug 2021–
Bucharest – Constanța railway (CFR Line 800) upgrade / Bucharest – ConstanțaRomaniaOpened225 kmJul 2014–
Frontieră – Curtici – Simeria railway rehabilitation (Corridor IV) / Section 1: Border – Curtici – Arad – km 614RomaniaOpened41 kmJan 2016+18 mo

Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.