Aktor
BulgariaGreeceRomaniaSerbia
- Sections
- 36
- Length
- 824 km
- Median slip
- +36 mo
- Median overrun
- –
Slip measured on 10 of 36 sections built.
No section this firm built records both an estimate and a final cost.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Joint ventures worked through
- AKTOR – Alstom Transport – Arcada Company
- AKTOR – J&P AVAX – INTRAKAT consortium
- AKTOR – TERNA – J&P AVAX
- Aktor – AVAX – ETETH JV
- Aktor – AVAX – TERNA JV
- Aktor – Michaniki – Techniki Olympiaki – I.G. Korontzis JV
- Aktor – Terna JV
- Apion Kleos Construction JV
- Kinopraxia Gefyra
- RailWorks
Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.
Sections built
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.