Astaldi

Romania
Sections
17
Length
502 km
Median slip
+22 mo
Median overrun

Slip measured on 8 of 17 sections built.

No section this firm built records both an estimate and a final cost.

Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.

Joint ventures worked through

  • Alstom Transport – Swietelsky – Astaldi – Euro Construct Trading '98 – Dafora
  • Astaldi / Max Bögl / CCCF
  • Astaldi – FCC – AB Construct – Delta ACM
  • Astaldi – Max Bögl
  • FCC Construcción – Astaldi
  • FCC – Astaldi – Convensa

Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.

Sections built

SectionCountryStatusLengthOpenedSlip
A1 Bucharest–Nădlac Motorway / Pitești – Curtea de Argeș (lot 5)RomaniaOpened30 kmJun 2025+17 mo
A1 Bucharest–Nădlac Motorway / Orăștie – SibiuRomaniaOpened82 kmNov 2014
A1 Bucharest–Nădlac Motorway / Arad – TimișoaraRomaniaOpened45 kmDec 2011
A1 Bucharest–Nădlac Motorway / Nădlac – Arad (Hungarian border)RomaniaOpened39 kmJul 2015
A2 Bucharest–Constanța Motorway / Drajna – FeteștiRomaniaOpened37 kmMay 2007+58 mo
A2 Bucharest–Constanța Motorway / Cernavodă – MedgidiaRomaniaOpened21 kmJul 2012+30 mo
A2 Bucharest–Constanța Motorway / Medgidia – MurfatlarRomaniaOpened16 kmJul 2012+24 mo
A2 Bucharest–Constanța Motorway / Murfatlar – ConstanțaRomaniaOpened21 kmSep 2011+14 mo
A4 motorway (Constanța bypass) / Ovidiu – DN3 interchangeRomaniaOpened11 kmJul 2012
A4 motorway (Constanța bypass) / DN3 interchange – Constanța West (A2 interchange)RomaniaOpened3 kmSep 2011
A4 motorway (Constanța bypass) / Constanța West (A2 interchange) – LazuRomaniaOpened5 kmJul 2011
Basarab Overpass, Bucharest / Nicolae Titulescu – Grozăvești overpassRomaniaOpened2 kmJun 2011+27 mo
Brăila Bridge / Main bridge and access roadsRomaniaOpened2 kmJul 2023+19 mo
Bucharest Metro Line M5 (Drumul Taberei) / Phase I: Râul Doamnei – Eroilor (with the Valea Ialomiței branch)RomaniaOpened7 kmSep 2020
Frontieră – Curtici – Simeria railway rehabilitation (Corridor IV) / Section 1: Border – Curtici – Arad – km 614RomaniaOpened41 kmJan 2016+18 mo
Frontieră – Curtici – Simeria railway rehabilitation (Corridor IV) / Section 2: km 614 – GurasadaRomaniaUnder construction100 km
Frontieră – Curtici – Simeria railway rehabilitation (Corridor IV) / Section 3: Gurasada – SimeriaRomaniaUnder construction41 km

Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.