FCC Construcción
PolandRomania
- Sections
- 18
- Length
- 453 km
- Median slip
- +55 mo
- Median overrun
- +12.4%
Slip measured on 6 of 18 sections built.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Joint ventures worked through
- Astaldi – FCC – AB Construct – Delta ACM
- FCC Construcción – Astaldi
- FCC Construcción – Gülermak – CCN
- FCC Construcción – PORR Bau
- FCC – Astaldi – Convensa
- Webuild – FCC Construcción – Salcef – Hitachi Rail
Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.
Sections built
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.