FCC Construcción
Romania
- Sections
- 10
- Length
- 233 km
- Median slip
- +33 mo
- Median overrun
- +12.4%
Slip measured on 2 of 10 sections built.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Joint ventures worked through
- Astaldi – FCC – AB Construct – Delta ACM
- FCC Construcción – Astaldi
- FCC – Astaldi – Convensa
Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.
Sections built
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.