Porr
Romania
- Sections
- 4
- Length
- 152 km
- Median slip
- +22 mo
- Median overrun
- –
Slip measured on 2 of 4 sections built.
No section this firm built records both an estimate and a final cost.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Joint ventures worked through
- FCC Construcción – Porr
Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.
Sections built
| Section | Country | Status | Length | Opened | Slip |
|---|---|---|---|---|---|
| A1 Bucharest–Nădlac Motorway / Curtea de Argeș – Boița (lots 2–4) | Romania | Under construction | 78 km | – | – |
| A1 Bucharest–Nădlac Motorway / Boița – Sibiu (lot 1) | Romania | Opened | 13 km | Dec 2022 | +11 mo |
| A1 Bucharest–Nădlac Motorway / Arad – Timișoara | Romania | Opened | 45 km | Dec 2011 | – |
| A10 motorway (Sebeș–Turda) / Lot 4: Decea – Turda (A3) | Romania | Opened | 16 km | Jul 2018 | +32 mo |
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.