Strabag
BulgariaCzechiaGermanyCroatiaHungaryPolandRomaniaSlovakia
- Sections
- 85
- Length
- 1,430 km
- Median slip
- +14 mo
- Median overrun
- –
Slip measured on 7 of 85 sections built.
No section this firm built records both an estimate and a final cost.
Only construction counts toward these figures. A design contract is listed on the firm's page and never folded in, because a construction overrun belongs to whoever built the thing.
Joint ventures worked through
- M0 Északi Duna-híd konzorcium
- M3 KRASZNA 2012 Konzorcium
- M5 Construction Group
- M5 Phase 3 Contractors
- Společnost Soběslav – Doubí
- Strabag BPA
- Strabag – Straco
- Strabag – Wilhelm Geiger
Work done in a joint venture is credited to each member firm, so a venture has no page of its own and never appears beside its members: that would count one section twice.
Sections built
Firms credited with at least 2 sections, worst median slip first. Measured exactly as on the performance page.